BLD-Final | 6/18/2018 | 6/19/2018 | 6/20/2018 | A | PART |
Dave Hannah
|
|
|
Tom--late morning is best Phone #: ###-#### ok for tco needs to fix gaurd rail ada hardware on sliding door plumbing co
|
FIRE-Final Inspection | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by south entry. Final life fire safety inspection complete.
Call to meet // Tom Phone #: ###-####
|
Print Occupancy Form | | | 6/12/2018 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PEND |
Dave Hannah
|
|
|
Call to meet there // Jake Phone #: ###-#### ok to cover after other trades ok rough ins
|
Route to Impact Fee Review | 10/29/2017 | 11/1/2017 | 10/30/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 10/30/2017 | | DONE |
|
|
|
NEED
GC -meg
Rev cert of val-met
|
Issue PAID IN FULL permit | | | 10/30/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/30/2017 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 10/14/2017 | 10/14/2017 | 10/29/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/23/2017 | | 10/29/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2017 | | DONE |
|
|
|
|
Routing - FIRE | 10/23/2017 | 10/23/2017 | 10/26/2017 | | PASS |
Scott Arellano
|
|
|
Revised comments attached to case
|
Plan assigned to (CJW) | 9/12/2017 | 9/12/2017 | 10/14/2017 | | DEFR |
Carl Westfall
|
|
|
(Oct 2 - 15 days) (37 sheets) Windermere Real Estate
|
Routing - PLAN CHECK | 9/12/2017 | | 10/14/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 10/14/2017 | | DONE |
Carl D Madsen
|
|
|
|
Routing - FIRE | 9/12/2017 | 9/12/2017 | 9/20/2017 | | FAIL |
Erika Akin
|
|
|
Emailed architect correction and attached to the case
|
Routing - Erosion and Sediment | 9/12/2017 | | 9/14/2017 | | PASS |
Andy J. Long
|
|
|
No exterior work. No ESC permit required upon initial review. Uncontained wallboard, paint, or other material washout on the exterior will be deemed a violation .
|
Routing - MECHANICAL | 9/12/2017 | | 9/14/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 9/12/2017 | | 9/13/2017 | | PASS |
Bill VanDegrift
|
|
|
minor plumbing remodel per plans and ISPC
|
Routing - Addressing | 9/12/2017 | | 9/12/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2017 | | 9/12/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 9/12/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl M approved pre screen
|
Application received | | | 9/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 1 2017 3:47PM
|