BLD-Final | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
DOC - Permit Finaled | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Other | 4/26/2018 | 4/26/2018 | 4/26/2018 | P | PASS |
Jim Storey
|
|
|
fire wall(garage) - mike Phone #: ###-####
|
BLD-Framing/Rough-in | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Wall Bracing | 3/30/2018 | 3/30/2018 | 3/30/2018 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Energy code compliance | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PART |
Jim Storey
|
|
|
mike Phone #: ###-#### floor truss cut/ fire blk 2nd floor ceilling mech chase.
|
BLD-Other | 3/8/2018 | 3/8/2018 | 3/8/2018 | P | PASS |
Jim Storey
|
|
|
Soffits - Mike Phone #: ###-####
|
BLD-Foundation | 3/5/2018 | 3/5/2018 | 3/5/2018 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Footing | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | PASS |
Jim Storey
|
|
|
close to 12- Mike Phone #: ###-####
|
BLD-Wall Bracing | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Brandon Shaw
|
|
|
Rusty Phone #: ###-####
|
BLD-Foundation | 1/22/2018 | 1/22/2018 | 1/22/2018 | A | DONE |
Jim Storey
|
|
|
mike by 316
|
BLD-Footing | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-#### Should be a Foundation Wall insp.
|
BLD-Footing | 1/17/2018 | 1/17/2018 | 1/17/2018 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/12/2018 | | DONE |
|
|
|
paid all project fees
|
Issue PAID IN FULL permit | | | 1/10/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 1/10/2018 | | |
|
|
|
still need to pay swr and achd impact fees
|
OVERRIDE | | | 12/1/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/1/2017 | | DONE |
|
|
|
All Met- Demo is included with this permit
|
Plan assigned to (M_H) | 10/25/2017 | | 12/1/2017 | | DONE |
Michael Hanson
|
|
|
10/16 sfd L1 ePlan - previous experience with same plan, sent back to applicant 10/25 MDH
|
Routing - PLAN CHECK | 10/25/2017 | | 12/1/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 11/22/2017 | | 11/22/2017 | | PASS |
Katelyn Menuge
|
|
|
|
Meeting | | | 11/3/2017 | | DONE |
|
|
|
added $2000.00 for demo valuation
|
Telephone call | | | 11/3/2017 | | DONE |
|
|
|
emailed Eric about park impact fees since the existing home will be demo'd before they start the new build
|
Telephone call | | | 11/2/2017 | | DONE |
|
|
|
called Mike-no demo permit but there was a house there already-left message to call me about both this one and the one next door BLD17-03181
|
Plan Reviewer's activity | | | 11/1/2017 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 11/1/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLANNING | 10/3/2017 | | 10/30/2017 | | FAIL |
Katelyn Menuge
|
|
|
Idaho Power approval and recorded Common Wall Agreement received.
|
Routing - PLAN CHECK | 10/3/2017 | | 10/25/2017 | | FAIL |
Brian McGowan
|
|
|
Multiple structural deficiences. Sent back to applicant 10/25 MDH
|
Route to Impact Fee Review | 10/3/2017 | 10/6/2017 | 10/6/2017 | | PASS |
Eric Bilimoria
|
|
|
Can not find the parcel in the GIS system, the building permit may have been assigned a temporary parcel number
|
Plan assigned to (BJM) | 10/3/2017 | 10/3/2017 | 10/3/2017 | | DEFR |
Brian McGowan
|
|
|
10/16 sfd L1 ePlan
|
Routing - Addressing | 10/3/2017 | | 10/3/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2017 | | 10/3/2017 | | PASS |
Morgan Webb
|
|
|
CREDIT FOR DEMO
|
Routing - MECHANICAL | 10/3/2017 | | 10/3/2017 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/3/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/3/2017 | | PASS |
|
|
|
|
Intake Approval | | | 9/22/2017 | | FAIL |
|
|
|
called Mike Cook, told him need to upload new parcel information from Ada County
|
Intake Approval | | | 9/13/2017 | | FAIL |
|
|
|
9-13-17 Parcel need to be recorded with Ada County and Boise City
|
Intake Approval | | | 9/12/2017 | | FAIL |
|
|
|
Needs to record original lots of record with Ada County Assessors office and Boise City. See checklist for other misc. items.
|
Application received | | | 9/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2017 8:06AM
|