Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-03183
StatusFinaled
Name CLINT ROBERTSON
Site Address 3020 W FAIRVIEW AVE
Project NameSilverdraft
Customer Number 
ePlanReviewYes
Description
(SILVERDRAFT)Permit for tenant improvement of office/warehouse space. Office tenant space 2,914 sq ft with warehouse 3,458 sq ft. Scope of work to include trash enclosure, parking area, loading area, restriping of parking lot. This tenant space was last occupied by RA Schultz and Company under BLD05-03253. This building is NOT fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/15/20185/11/2018 DONE
mailed 5-14
Third Notice 3/19/20184/10/2018 DONE
mailed 4-11-18
Second Notice 2/22/20183/14/2018 DONE
Mailed 3-15-18
First Notice 2/2/20182/12/2018 DONE
Mailed 2-13-18
Print Occupancy Form  1/23/2018 DONE
Permanent Occupancy  1/23/2018 DONE
Zoning Approval1/19/20181/19/20181/19/2018 DONE
DetailsAndrea Tuning
BLD-Final1/17/20181/18/20181/18/2018PPASS
DetailsDave Hannah
Please contact Clint prior to going out. Phone #: ###-####
FIRE-Final Inspection1/17/20181/17/20181/17/2018PPASS
DetailsJim Page
Previously noted items have been completed, no fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
FIRE-Final Inspection1/11/20181/12/20181/12/2018PFAIL
DetailsTroy Cobbley
I left two messages on the contacts voice mail and also went to the project site. I was unable to test the exit discharge lights and I also noted that a building address was missing.

Clint Phone #: ###-####
BLD-Final12/1/201712/5/201712/5/2017PCANC
DetailsDave Hannah
Clint Phone #: ###-####
BLD-Foundation12/1/201712/4/201712/4/2017PDONE
DetailsDave Hannah
Please call ahead for access, requesting after 3 - Clint Phone #: ###-####
FIRE-Final Inspection12/1/201712/4/201712/4/2017PFAIL
DetailsJim Page
THumbturn deadbolt on southeast door needs to be changed to a double-keyed deadbolt. Fire extinguishers need to be inspected by a licensed contractor and tagged accordingly. Provide emergency lighting for the exit discharge as stated in note number 7 of the building permit fire code review.
Issue PAID IN FULL permit  10/31/2017 DONE
Print Occupancy Form  10/31/2017 DONE
OVERRIDE  9/29/2017  
Plan assigned to (AJS)9/7/20179/7/20179/29/2017 PASS
DetailsAdele J Schaffeld-Griffin
Building Review completed
Routing - PLAN CHECK9/29/2017 9/29/2017 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  9/29/2017 DONE
Permit Ready to Issue  9/29/2017 DONE
NEED:
GC
rev cert of val
RP
Routing - Erosion and Sediment9/25/2017 9/27/2017 PASS
DetailsAndy J. Long
ESC plan waiver approved. Need RP at time of permit issuance.
Route to Impact Fee Review9/20/20179/23/20179/22/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - Erosion and Sediment9/20/2017 9/22/2017 FAIL
DetailsAndy J. Long
Project includes exterior work for parking area and will also have staging and waste management areas exposed during construction. Please submit ESC plan or ESC plan waiver request.
1st review completed  9/20/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK9/20/2017 9/20/2017 PASS
DetailsAdele J Schaffeld-Griffin
Routing - Design Review9/20/2017 9/20/2017 PASS
DetailsAndrea Tuning
Routing - FIRE9/7/20179/7/20179/19/2017 PASS
DetailsErika Akin
Attached comments to case
Routing - Design Review9/7/2017 9/18/2017 FAIL
DetailsAndrea Tuning
All parking areas, drive aisles and loading areas shall provide a 5-foot side and rear setbacks.

All parking, drive aisles and loading areas shall be paved.

Relocate the trash enclosure to be outside of the 10-foot front setback. The enclsoure shall also be screened from public view through the use of sight obscuring fencing or landscaping.
Routing - PLAN CHECK9/7/2017 9/12/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - Addressing9/7/2017 9/8/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/7/2017 9/8/2017 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment9/7/2017 9/8/2017 FAIL
DetailsAndy J. Long
Project includes exterior work for parking area and will also have staging and waste management areas exposed during construction. Please submit ESC plan or ESC plan waiver request.
Intake Approval  9/7/2017 PASS
DetailsAdele J Schaffeld-Griffin
Application received  9/5/2017 DONE
Application submitted via PDS Online on Sep 5 2017 1:01PM