Letter of compliance/Occupancy | | | 6/25/2018 | | DONE |
|
|
|
|
BLD-Final | 6/6/2018 | 6/12/2018 | 6/12/2018 | P | PASS |
Tony Young
|
|
|
Chad Phone #: ###-####,,
|
DOC - Permit Finaled | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | PASS |
Tony Young
|
|
|
|
PubWorks Occupancy Approval | 6/11/2018 | 6/11/2018 | 6/11/2018 | | DONE |
Jason C. Taylor
|
|
|
|
Elevation Cert Rec'd-Final | | | 6/11/2018 | | DONE |
|
|
|
|
BLD-Final | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PART |
Tony Young
|
|
|
Chad Phone #: ###-####,, final ok after public works passes flood plain
|
BLD-Final | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | NR |
Tony Young
|
|
|
Chad Phone #: ###-####,, needs flood plain final,, steps out of the house into the garage
|
BLD-Energy code compliance | 3/16/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Tony Young
|
|
|
Please call chad with any questions Phone #: ###-#### Inspection requested via web by Chad Aland
|
BLD-Framing/Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
Elevation Cert Rec'd-Midconst | | | 3/12/2018 | | DONE |
|
|
|
|
BLD-Energy code compliance | 3/7/2018 | 3/8/2018 | 3/8/2018 | A | FAIL |
Dave Hannah
|
|
|
Please call Chad 30 minutes prior to inspection, I would like to be on site if possible.
Phone #: ###-#### Inspection requested via web by Chad Aland needs flood plan cert no inspection done
|
Plan Modification Accepted | | | 2/20/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 2/20/2018 | | 2/20/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chad Aland
|
BLD-Wall Bracing | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | DEFR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chad Aland
|
BLD-Wall Bracing | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chad Aland
|
Telephone call | | | 12/21/2017 | | DONE |
|
|
|
customer called to pull plumbing permit-removed hold so he could pull permit and will put back on once the plm permit is pulled.
they pulled the permit and i put the hold back on but the note isn't exactly what JCT usually puts in because I forgot what all it said and my copy/paste didn't work
|
BLD-Foundation | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | NR |
Dave Hannah
|
|
|
Ricardo- (reminded them they need to turn in another elevation certificate before framing inpsection) Phone #: ###-####
|
BLD-Footing | 12/1/2017 | 12/4/2017 | 12/4/2017 | P | PASS |
Tony Young
|
|
|
Ricardo Phone #: ###-####
|
Override - Condition Holds | 12/1/2017 | 1/1/1900 | 12/1/2017 | | |
|
|
|
Footing inspection only
|
Override - Condition Holds | | | 11/27/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/27/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/27/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/22/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/22/2017 | | DONE |
Michael Hanson
|
|
|
|
Override - Condition Holds | | | 11/22/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 11/22/2017 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 10/13/2017 | | 11/22/2017 | | DONE |
Michael Hanson
|
|
|
9/29 sfd L2 ePlan - Failed due to structural deficiencies added changemarks and returned to applicant. 10/16/2017 MDH Reviewed resubmittal pass residential plan review but needs flood plain review by Jason Taylor 10/23 MDH
|
Routing - PLAN CHECK | 11/22/2017 | | 11/22/2017 | | PASS |
Josh Bogle
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 11/17/2017 | | DONE |
|
|
|
|
Routing PW Flood Plain | 11/17/2017 | | 11/17/2017 | | PASS |
Jason C. Taylor
|
|
|
|
1st review completed | | | 11/7/2017 | | DONE |
Michael Hanson
|
|
|
|
Plan Reviewer's activity | | | 11/7/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing PW Flood Plain | 10/25/2017 | | 10/26/2017 | | FAIL |
Jason C. Taylor
|
|
|
see changemarks in ePlan. JCT
|
Routing PW Flood Plain | 9/14/2017 | | 9/20/2017 | | FAIL |
Jason C. Taylor
|
|
|
see changemarks in ePlan. JCT
|
Route to Impact Fee Review | 9/14/2017 | 9/17/2017 | 9/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 9/14/2017 | 9/14/2017 | 9/14/2017 | | DEFR |
Brian McGowan
|
|
|
10/03 sfd L2 ePlan
|
Routing - MECHANICAL | 9/14/2017 | | 9/14/2017 | | FAIL |
Troy James
|
|
|
Emailed corrections to legends mech
|
Routing - PLANNING | 9/14/2017 | | 9/14/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 9/14/2017 | | 9/14/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/14/2017 | | 9/14/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 9/14/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/14/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/14/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 9/14/2017 | | 9/14/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 9/12/2017 | | FAIL |
|
|
|
Drawings must be uploaded individually and facing the correct way. Bottom right corner needs to be left blank for the cities stamp.
Once drawings are uploaded correctly, I will do the plan pre-screen. Thanks
|
Application received | | | 9/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 6 2017 12:54PM
|