BLD-Final | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | DONE |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth
|
FIRE-Final Inspection | 2/17/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Fire Life Phone #: ###-#### Inspection requested via web by Amanda Farnsworth
|
FIRE-Final Inspection | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | FAIL |
Troy Cobbley
|
|
|
The engineer's details for the notification height state the device is to be mounted between 80" and 96". All of the devices have been mounted above the stated limits.
Life safety Phone #: ###-#### Inspection requested via web by Amanda Farnsworth
|
FIRE-Final Inspection | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans and the letter from the engineer as discussed for the gas system.
Ryan Phone #: ###-####
|
BLD-Final | 2/10/2020 | 2/10/2020 | 2/11/2020 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth
|
BLD-Final | 2/7/2020 | 2/10/2020 | 2/11/2020 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth
|
BLD-Aging Inspection | 1/27/2020 | 1/27/2020 | 1/27/2020 | | NR |
Jim Storey
|
|
|
425
|
BLD-Final | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth
|
Telephone call | | | 3/14/2019 | | DONE |
|
|
|
called to see if Amanda could sent the signed permit back to me-left message on her phone
|
Telephone call | | | 3/13/2019 | | DONE |
|
|
|
spoke with Jim Dong, he stated that the project should be done by next month. Informed him that there shouldn't be any work going on since they do not have their permit no the approved plans. Told him we need the 302 and 306 from the GC and have this permit paid for right away since they are working
|
Issue PAID IN FULL permit | | | 3/13/2019 | | DONE |
|
|
|
emailed AMANDAR@HOBSONFAB.COM to sign the permit
|
Inspection Record Card- Bld | | | 3/13/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/11/2019 | | DONE |
|
|
|
called jake back informing him that we still need the GC to send in a 302 and 306 and have the permit paid for/picked up by 5pm Friday (15th) since it's pass the date and has had two extensions
|
Telephone call | | | 2/28/2019 | | DONE |
|
|
|
left a message with jacob, jim's number no longer works, informing him that that permit is going to expire at 5pm today and is welcome to send in a request for a 180 day extension.
|
Meeting | | | 2/4/2019 | | DONE |
|
|
|
sent email to jim, see documents, stating this permit will expire 2/28/19 and has already had two extensions
|
Extend Review Timeline | | | 12/17/2018 | | DONE |
|
|
|
Final & 1st approved 180 day extension per Adele. see documents
|
Meeting | | | 12/12/2018 | | DONE |
|
|
|
Jim Dong sent in request for two 180 day extensions
|
Meeting | | | 12/11/2018 | | DONE |
|
|
|
sent email to Jim (jd@raymundo.com) recommend to send in a request for two 180 day extensions. see documents
|
Plan assigned to (JG) | 8/9/2018 | 8/9/2018 | 12/6/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 8/15 L2 VRT BMF HVAC & CNG Redesign ePlan
|
Routing - PLAN CHECK | 11/29/2018 | | 12/6/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/6/2018 | | DONE |
|
|
|
MET AMANDAR@HOBSONFAB.COM
Need
GC Form
Revised Cert of Value
|
Routing - MECHANICAL | 11/29/2018 | | 11/29/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/22/2018 | 8/25/2018 | 8/22/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/22/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 8/9/2018 | 8/9/2018 | 8/21/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 8/9/2018 | | 8/18/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 8/9/2018 | | 8/14/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 8/9/2018 | | 8/13/2018 | | FAIL |
Troy James
|
|
|
Existing gas piping is undersized for the new btu load.
|
Routing - PLUMBING | 8/9/2018 | | 8/10/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 8/9/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
Corrected address: 4701 S Northrup St
|
Routing - PUBLIC WORKS | 8/9/2018 | | 8/9/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 8/9/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 8/9/2018 | | 8/9/2018 | | PASS |
Andrea Tuning
|
|
|
No review required
|
Intake Approval | | | 9/26/2017 | | FAIL |
Michael Hanson
|
|
|
Entered by CJW for Michael Hanson
|
Intake Approval | | | 9/11/2017 | | FAIL |
Michael Hanson
|
|
|
Entered by CJW for Michael Hanson
|
Application received | | | 9/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 6 2017 4:41PM
|