BLD-Final | 3/23/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
DOC - Permit Finaled | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 3/21/2018 | 3/21/2018 | 3/21/2018 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart,, needs a protection post in front of water heater/furnace, fire caulk,, exterior siding seal around wires,, etc
|
BLD-Energy code compliance | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Framing/Rough-in | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart,, corrections,, ok to insulate
|
BLD-Wall Bracing | 12/26/2017 | 12/26/2017 | 12/26/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Foundation | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PART |
Tony Young
|
|
|
Wall // Ryan Phone #: ###-####
|
BLD-Footing | 10/27/2017 | 10/27/2017 | 10/27/2017 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, need to dig out loose and make grade on pad footings prior to pouring
|
Issue PAID IN FULL permit | | | 10/11/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/10/2017 | | |
|
|
|
|
Plan assigned to (RDP) | 10/6/2017 | 10/6/2017 | 10/10/2017 | | DONE |
Rob Patrick
|
|
|
SENT TO BRIAN FOR CHECKING
|
Plan Reviewer's activity | | | 10/10/2017 | | DONE |
Rob Patrick
|
|
|
|
1st review completed | | | 10/10/2017 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2017 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/10/2017 | | DONE |
|
|
|
all met
|
Routing - PLAN CHECK | 9/12/2017 | | 10/10/2017 | | PASS |
Brian McGowan
|
|
|
|
Plan assigned to (BJM) | 9/12/2017 | 9/12/2017 | 10/6/2017 | | DEFR |
Brian McGowan
|
|
|
9/25 sfd L1 ePlan
|
Route to Impact Fee Review | 9/12/2017 | 9/15/2017 | 9/14/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 9/12/2017 | | 9/13/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/12/2017 | | 9/13/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 9/12/2017 | | 9/12/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2017 | | 9/12/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/12/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/12/2017 | | DONE |
|
|
|
|
Intake Approval | | | 9/12/2017 | | PASS |
|
|
|
|
Application received | | | 9/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 11 2017 10:47AM
|