BLD-Final | 6/7/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Brandon Shaw
|
|
|
Bill Phone #: ###-####
|
DOC - Permit Finaled | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Framing/Rough-in | 2/9/2018 | 2/12/2018 | 2/12/2018 | A | PASS |
Jim Storey
|
|
|
First thing if possible - Bill Phone #: ###-####
|
BLD-Other | 2/8/2018 | 2/8/2018 | 2/8/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Wall Bracing | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Brandon Shaw
|
|
|
Shear // Daryl Phone #: ###-####
|
Plan Modification Accepted | | | 1/11/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/11/2018 | | 1/11/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 11/10/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Conference | 11/11/2017 | 11/13/2017 | 11/13/2017 | A | CANC |
Brandon Shaw
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Conference | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
Plan assigned to (M_H) | 10/11/2017 | | 10/23/2017 | | DONE |
Michael Hanson
|
|
|
10/04 sfd ePlan - 1st review complete sent to CDM 10/13 MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 10/23/2017 | | DONE |
|
|
|
all met
|
Issue PAID IN FULL permit | | | 10/23/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/2017 | | DONE |
|
|
|
|
1st review completed | | | 10/19/2017 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 9/21/2017 | | 10/19/2017 | | PASS |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 10/13/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 9/21/2017 | | 9/25/2017 | | PASS |
Troy James
|
|
|
|
Routing PW Flood Plain | 9/21/2017 | | 9/22/2017 | | PASS |
Jason C. Taylor
|
|
|
LOMR on file for this lot. No floodplain requirements needed. JCT
|
Routing PW Sewer Rating | 9/22/2017 | | 9/22/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan assigned to (BJM) | 9/21/2017 | 9/21/2017 | 9/21/2017 | | DEFR |
Brian McGowan
|
|
|
10/04 sfd L1 ePlan
|
Intake Approval | | | 9/21/2017 | | FAIL |
|
|
|
need to upload plans in landscape position.
|
Intake Approval | | | 9/21/2017 | | PASS |
|
|
|
|
Routing - PLANNING | 9/21/2017 | | 9/21/2017 | | PASS |
Sue Cummings
|
|
|
|
Route to Impact Fee Review | 9/18/2017 | 9/21/2017 | 9/19/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/18/2017 | | DONE |
|
|
|
|
Intake Approval | | | 9/18/2017 | | FAIL |
|
|
|
Need to flip house, will resubmit all new plans and manual J
|
Routing - Addressing | 9/18/2017 | | 9/18/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/18/2017 | | 9/18/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 9/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 13 2017 3:24PM
|