BLD-Final | 5/4/2018 | 5/4/2018 | 5/4/2018 | P | PASS |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
DOC - Permit Finaled | 5/4/2018 | 5/4/2018 | 5/4/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 5/2/2018 | 5/3/2018 | 5/3/2018 | A | FAIL |
Mike Jordan
|
|
|
Joe-garage code is 4200 Phone #: ###-####. Insulate crawl space and complete grading away from foundation.
|
BLD-Blower Door Test Results | 5/3/2018 | 5/3/2018 | 5/3/2018 | A | DONE |
Mike Jordan
|
|
|
Joe-garage code is 4200 Phone #: ###-####
4.68
|
BLD-Energy code compliance | 3/8/2018 | 3/8/2018 | 3/8/2018 | P | PASS |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
BLD-Framing/Rough-in | 3/2/2018 | 3/5/2018 | 3/5/2018 | A | NR |
Mike Jordan
|
|
|
Joe Phone #: ###-#### NeedsMech. rough ininspection.
|
BLD-Conference | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | CANC |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
BLD-Wall Bracing | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | PASS |
Jim Sly
|
|
|
Shear // Joe Phone #: ###-####
|
BLD-Wall Bracing | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | FAIL |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Missing blocking on edges at front bedroom next to garage. block and nail.
|
BLD-Wall Bracing | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | NR |
Mike Jordan
|
|
|
Joe Phone #: ###-####. No city approved plans on site.
|
BLD-Footing | 11/22/2017 | 11/27/2017 | 11/27/2017 | A | PART |
Mike Jordan
|
|
|
Mersadees Phone #: ###-####. Footings and set backs appear ok per provided plans. Approved plans not on site. Contractor proceeds at own risk.
|
BLD-Footing | 11/21/2017 | 11/22/2017 | 11/22/2017 | A | NR |
Mike Jordan
|
|
|
mersadees Phone #: ###-####. no one on site. No plans on site.
|
BLD-Footing | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | CANC |
Mike Jordan
|
|
|
Joe ###-####. Cancelled per concrete contractor. Noted missing property pins.
|
Issue PAID IN FULL permit | | | 11/20/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/16/2017 | | |
|
|
|
|
Plan assigned to (RDP) | 10/10/2017 | 10/10/2017 | 10/16/2017 | | DONE |
Rob Patrick
|
|
|
|
1st review completed | | | 10/16/2017 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 10/16/2017 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2017 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 10/16/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/16/2017 | | DONE |
|
|
|
all met
|
Telephone call | | | 10/16/2017 | | DONE |
|
|
|
Called Joseph Bureau and told him permit is ready and fee due.
|
Routing - PLAN CHECK | 9/20/2017 | | 10/13/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 9/18/2017 | | 10/13/2017 | | PASS |
Colleen T Carroll
|
|
|
|
Plan Reviewer's activity | | | 10/10/2017 | | DONE |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 9/21/2017 | | 9/21/2017 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | | | 9/20/2017 | | FAIL |
Troy James
|
|
|
emailed correction to idaho hvac
|
Route to Impact Fee Review | 9/15/2017 | 9/18/2017 | 9/19/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/15/2017 | | 9/18/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/15/2017 | | 9/18/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan assigned to (BJM) | 9/15/2017 | 9/15/2017 | 9/15/2017 | | DEFR |
Brian McGowan
|
|
|
9/28 sfd L1 paper
|
Plans ACCEPTED BY PLAN TECH | | | 9/15/2017 | | DONE |
|
|
|
|
Intake Approval | | | 9/15/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/15/2017 | | DONE |
|
|
|
|
Application received | | 9/15/2017 | | | |
|
|
|
|