Permit Information
Permit NumberBLD17-03395
StatusFinaled
Name CUSTOM STEEL STRUCTURES
Site Address 5100 W BETHEL ST
Project NameBoise River Fence
Customer Number 
ePlanReviewNo
Description
(BOISE RIVER FENCE - METAL OFFICE/FABRICATION BUILDING) (DRH17-00315) **Permit for the shell/core construction of a new 10,400 sq. ft. pre-engineered shell building under BLD17-03395, new 576 sq ft pre-engineered shell building for wash bay under BLD17-03396, and related site improvements. Scope of work includes: construction of slab on grade concrete foundation, pre-engineered shell with insulation, mezzanine with stairs and guardrail, interior non-bearing walls, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. All work shall comply with the approved plans, DRH16-00273 and all applicable codes. This building is NOT Fire Sprinklered. Note: Special Inspections Required, see form 310. Note: complies with ANSI/ASHREA 90.1. Mechanical, Electrical, and Plumbing are not included under this permit and will require separate 520 TI Permit Application for Certificate of Occupancy. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/4/201911/25/2019 DONE
mailed 12-2-19
First Notice 9/29/201910/25/2019 DONE
mailed 11-1-19
FIRE-Final Inspection9/18/20199/18/20199/19/2019PPASS
DetailsTroy Cobbley
Life safety passed. Fire Station #6 verified that the opticon functioned. Curt Phone #: ###-####
Letter of compliance/Occupancy  9/19/2019 DONE
DOC - Permit Finaled  9/19/2019 DONE
passed final inspection
BLD-Final9/18/20199/18/20199/18/2019PPASS
DetailsTell Riley
Curtis Phone #: ###-####//per Jim Sly's notes final is complete and passed when fire/life safety is passed//
PubWorks Occupancy Approval8/6/20198/6/20198/6/2019 DONE
DetailsTiffany Lowery
BLD-Final1/2/20191/3/20191/3/2019APART
DetailsJim Sly
Call ahead // Curt Phone #: ###-####
OK for Temp Occ. OK for Perm Occ. when Fire/ Life signs off perm. and Public Works signs off perm.
BLD-Final12/27/201812/28/201812/28/2018PNR
DetailsDave Hannah
Curt Phone #: ###-####
BLD-Conference12/21/201812/26/201812/26/2018APART
DetailsTony Young
Kurt Phone #: ###-####,, walk through,, needs trades
Zoning Approval12/21/201812/21/201812/21/2018 PASS
DetailsKatelyn Menuge
DRH17-00315
FIRE-Final Inspection12/18/201812/19/201812/19/2018APART
DetailsTroy Cobbley
Temp until the fence/gate is installed


curt Phone #: ###-####
FIRE-Final Inspection12/18/201812/18/201812/18/2018PFAIL
DetailsTroy Cobbley
Gate has not been installed yet. I went over the review comments that address the gate.
PubWorks Temp Occupancy Appr12/13/201812/13/201812/13/2018 DONE
DetailsTiffany Lowery
BLD-Framing/Rough-in10/17/201810/18/201810/18/2018APART
DetailsJim Sly
Kurt Phone #: ###-####
All Ok except......C/N.......Rise on stairway is 7 1/2........need 7.
Telephone call  9/12/2018 DONE
called Curt Barber. Zoning inspection added to required signatures. will email new inspection card to him.
Inspection Record Card- Bld  9/12/2018 DONE
emailed new card with updated required signatured (added zoning) to Curt Barber.
Issue PAID IN FULL permit  2/22/2018 DONE
Expiration Notice2/21/20183/14/20182/21/2018 DONE
DetailsBrittany Hill
Telephone call  1/29/2018 DONE
Called Richard to inform him that the permit is ready to be picked up, we need the GC form, Revised Cert of value and either a reciept or a letter from ACHD about Impact fees.
Routing - PUBLIC WORKS1/26/2018 1/29/2018 PASS
DetailsMorgan Webb
OVERRIDE  1/26/2018  
Plan assigned to (JAR)9/22/20179/22/20171/26/2018 DONE
DetailsJulie Romig
**1st Rev Comp - 2nd Rev Comp - 502 Boise River Fence
Routing Off Site - STRUCTURAL1/23/2018 1/26/2018 PASS
DetailsJulie Romig
Inspection Record Card- Bld  1/26/2018 DONE
Permit Ready to Issue  1/26/2018 DONE
DetailsChristina Prado
Need:
ACHD-met

MET
GC
Revised Value
PLANS/APPL TAKEN TO FRONT DESK  1/26/2018 DONE
Case Summary (BLD)  1/26/2018 DONE
Plan resubmittals received  1/23/2018 DONE
received three copies of response memos, structural calcs, and plan sheet A2.0; taken to Julie R.
Telephone call  1/23/2018 DONE
DetailsChristina Prado
called courier for pick up to AHJ
Routing PW Sewer Design1/22/2018 1/22/2018 PASS
DetailsMike Sheppard
Project plans have met sewer requirements
Routing - PLAN CHECK1/16/2018 1/18/2018 PASS
DetailsJulie Romig
Pending structural and public works review
Routing Off Site - STRUCTURAL12/21/2018 1/18/2018 FAIL
DetailsJulie Romig
2nd Review - Plan Review report emailed to architect.
Routing - FIRE1/17/20181/17/20181/17/2018 PASS
DetailsErika Akin
Attached comments to case and plans
Routing - Design Review1/16/2018 1/16/2018 PASS
DetailsKatelyn Menuge
Routing PW Sewer Design1/11/2018 1/16/2018 FAIL
DetailsMike Sheppard
Routing PW Sewer Rating12/26/2017 1/16/2018 PASS
DetailsMorgan Webb
Routing - PUBLIC WORKS12/26/2017 1/16/2018 FAIL
DetailsRachael Beierle
FAIL. SEE MIKE SHEPPARD
Routing PW Solid Waste1/11/2018 1/12/2018 PASS
DetailsEvan Carpenter
Plan resubmittals received  12/20/2017 DONE
received architects response, three copies of Suez water flow sheet, Envelope Compliance Cert, structural calcs for mezzanine/covered entry/wash bay, plan sheets 1,2,3,4,5,6, A0.0, A0.1, A1.0, A1.1, A2.0, 3.0, 3.1; taken to Julie Romig
Meeting  12/4/2017 DONE
DetailsScott Arellano
Met with Rick George and reviewed the Fire Code plan review report. We discussed options for meeting fire hydrant requirements and the code benenfits of fire sprinklers in the proposed structure. I advised Rick to contact SUEZ water for an accurate estimate on fire hydrant installation costs and to approximate specific hydrant locations on the existing roadway which may qualify for the current project.
Route to Impact Fee Review11/3/201711/6/201711/7/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE  11/3/2017 FAIL
DetailsErika Akin
Attached review comments to case and emailed architect
1st review completed  11/3/2017 DONE
DetailsJulie Romig
Routing - PLAN CHECK  11/1/2017 FAIL
DetailsJulie Romig
IBC Plan Review Report emailed to Architect/Owner/Contractor.
Routing - Design Review  10/6/2017 FAIL
DetailsKatelyn Menuge
DRH17-315 Katelyn Corrections Requries, see site plan
Routing - Erosion and Sediment10/4/2017 10/5/2017 PASS
DetailsAndy J. Long
ESC plan approved. Certified stormwater team designated. No ESC site preparation inspection is required. Only one ESC permit is required for both BLD17-03395 & -03396.
Routing - PUBLIC WORKS  10/4/2017 FAIL
Routing Off Site - STRUCTURAL9/22/2017 10/4/2017 FAIL
DetailsJulie Romig
Structural Plan Review Report emailed to applicant.
Routing PW Sewer Design  10/4/2017 FAIL
DetailsKyle S. Rosenmeyer
Use existing sewer service if at all possible. If existing service is not used, abandon it and cap it at the main. Tap the new sewer service in as a type "D" per ISPWC using an insert-a-tee connection. Tap and Plug permist required from Boise Public Works 48 hours prior to construction.
Routing PW Sewer Rating  10/4/2017 FAIL
DetailsMorgan Webb
Routing PW Drainage9/29/2017 10/3/2017 PASS
DetailsBrian Murphy
Routing PW Solid Waste9/27/2017 9/28/2017 FAIL
DetailsEvan Carpenter
The solid waste enclosure must have at least 12 feet of unobstructed clearance between gate posts.

There needs to be 50 feet of clearance in front of the enclosure gate to ensure that the dumpster can be serviced properly.
Routing PW Environmental9/25/2017 9/27/2017 PASS
DetailsRick Christenson
Routing PW Street Lights9/27/2017 9/27/2017 PASS
DetailsTom Marshall
Routing - PLANNING Land Div9/22/2017 9/25/2017 PASS
DetailsTodd Tucker
Routing - Addressing9/25/2017 9/25/2017 PASS
DetailsDoug Chausow
Updated parcel and address to 5100 W Bethel St
Telephone call  9/22/2017 DONE
called Action Couriers for pick up to outside engineering
Intake Approval  9/21/2017 PASS
Per JG
Plans ACCEPTED BY PLAN TECH  9/21/2017 DONE
Recd Pcfee & Taken To Pln CK  9/21/2017 DONE
Application received 9/21/2017