BLD-Blower Door Test Results | 7/16/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall 5.0
|
BLD-Final | 7/16/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 5/16/2018 | 5/16/2018 | 5/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Energy code compliance | 5/15/2018 | 5/16/2018 | 5/16/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Framing/Rough-in | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | FAIL |
Brandon Shaw
|
|
|
Hold downs to be installed per Manuf. recommendation. Interior shear walls need edges blocked and nailing, as per plans.
OK to insulate
|
BLD-Other | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | PASS |
Brandon Shaw
|
|
|
soffit-fire rating, Ever Phone #: ###-####
|
BLD-Wall Bracing | 4/6/2018 | 4/6/2018 | 4/6/2018 | P | PART |
Brandon Shaw
|
|
|
Hold downs and straps to be installed before framing rough in.
|
Place hold on job | 10/25/2017 | | 10/25/2017 | | DONE |
Tiffany Carson-Herker
|
|
|
waiting for signed bld back so we can release approved plans
|
OVERRIDE | | | 10/23/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 10/20/2017 | 10/20/2017 | 10/23/2017 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 10/23/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 10/23/2017 | | DONE |
|
|
|
All met
|
Issue PAID IN FULL permit | | | 10/23/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/26/2017 | | 10/23/2017 | | PASS |
Josh Bogle
|
|
|
|
Routing - Addressing | 9/26/2017 | | 10/23/2017 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 9/26/2017 | 9/29/2017 | 9/27/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 9/26/2017 | | 9/27/2017 | | PASS |
Susan Riggs
|
|
|
Note, garage must be setback a minimum 20' from private drive.
|
Plan assigned to (BJM) | 9/26/2017 | 9/26/2017 | 9/26/2017 | | DEFR |
Brian McGowan
|
|
|
10/09 sfd L1 ePlan
|
Intake Approval | | | 9/26/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/26/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/26/2017 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/26/2017 | | 9/26/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 9/26/2017 | | 9/26/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Application received | | | 9/25/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 25 2017 10:05AM
|