BLD-Final | 12/28/2017 | 12/28/2017 | 12/28/2017 | P | NR |
Mike Jordan
|
|
|
Austin Phone #: ###-####. Needs to complete roofing. everything else ok.
|
BLD-Framing/Rough-in | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. North half ok.
|
BLD-Footing | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | PASS |
Brandon Shaw
|
|
|
Late morning // John Phone #: ###-####
|
BLD-Footing | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | PASS |
Mike Jordan
|
|
|
Gregg Phone #: ###-####
|
PubWorks Subgrade Approval | 10/23/2017 | 10/23/2017 | 10/23/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 10/19/2017 | 10/20/2017 | 10/20/2017 | A | FAIL |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Needs to submit letter from geotech engineer approving the subgrade. Greg was notified via phone call.
|
OVERRIDE | | | 9/28/2017 | | |
|
|
|
|
Routing Walk-In (PW Hillside) | 9/28/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (Zoning) | 9/28/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 9/28/2017 | 9/28/2017 | 9/28/2017 | A | DONE |
Josh Bogle
|
|
|
|
1st review completed | | | 9/28/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 9/28/2017 | | 9/28/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 9/28/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/28/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 9/28/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/28/2017 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 9/27/2017 | 9/27/2017 | 9/27/2017 | A | FAIL |
Josh Bogle
|
|
|
Needs a CUP to extend in front of house or attach
|
Application received | | 9/27/2017 | | | |
|
|
|
|