BLD-Final | 11/26/2018 | 11/30/2018 | 11/30/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/26/2018 | 11/30/2018 | 11/30/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.2
|
PubWorks Occupancy Approval | 11/21/2018 | 11/21/2018 | 11/21/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 9/4/2018 | 9/6/2018 | 9/6/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 8/28/2018 | 9/4/2018 | 9/4/2018 | A | PEND |
Brandon Shaw
|
|
|
Hold downs to be as per plans, installed per manufact. install. instructions
OK to insulate
|
BLD-Wall Bracing | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PEND |
Brandon Shaw
|
|
|
Missing straps and hold downs to be installed before framing rough in...
|
BLD-Foundation | 6/26/2018 | 6/26/2018 | 6/26/2018 | A | PASS |
Brandon Shaw
|
|
|
|
BLD-Footing | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | NR |
Brandon Shaw
|
|
|
Brian Phone #: ###-####
|
PubWorks Subgrade Approval | 6/14/2018 | 6/14/2018 | 6/14/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 4/19/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 9/28/2017 | 9/28/2017 | 4/19/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete 2-5 Corrections requested-Need Hillside to final. 10/18 sfd L2 ePlan
|
Issue PAID IN FULL permit | | | 4/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/19/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/17/2018 | | 4/19/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/19/2018 | | DONE |
|
|
|
met
|
Telephone call | | | 4/10/2018 | | DONE |
|
|
|
Josh emailed asking about the status of this permit. I emailed him back that the permit was in the building dept and was the last one to review the resubmittals
|
Routing PW Grading-Hillside | 2/26/2018 | | 2/26/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing PW Grading-Hillside | 2/1/2018 | | 2/2/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan
|
Routing - PUBLIC WORKS | 2/1/2018 | | 2/1/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLAN CHECK | 1/31/2018 | | 1/31/2018 | | FAIL |
Brian McGowan
|
|
|
Need Hillside Changemarks resolved. Sheet sizes must match
|
Routing PW Grading-Hillside | 1/11/2018 | | 1/11/2018 | | FAIL |
Jason C. Taylor
|
|
|
see changemarks in eplan. JCT
|
Routing PW Grading-Hillside | 11/6/2017 | | 11/6/2017 | | FAIL |
Melissa Jannusch
|
|
|
see changemarks in ePlan
|
1st review completed | | | 10/31/2017 | | FAIL |
Brian McGowan
|
|
|
Top of FND and FTG needed. Garage beam verification.
|
Routing - PLAN CHECK | 9/28/2017 | | 10/31/2017 | | FAIL |
Brian McGowan
|
|
|
Top of FND and FTG needed. Garage beam verification.
|
Routing - FIRE | 9/28/2017 | 9/28/2017 | 10/2/2017 | | PASS |
Scott Arellano
|
|
|
NO comments attached.
|
Routing - MECHANICAL | 9/28/2017 | | 10/2/2017 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 9/28/2017 | | 10/2/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid stormwater and pollution prevention team designated. Site preparation inspection is required.
|
Route to Impact Fee Review | 9/28/2017 | 10/1/2017 | 9/29/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Intake Approval | | | 9/28/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/28/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/28/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 9/28/2017 | | 9/28/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 9/28/2017 | | 9/28/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/28/2017 | | 9/28/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Grading-Hillside | 9/28/2017 | | 9/28/2017 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan
|
Application received | | | 9/27/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2017 11:12AM
|