BLD-Aging Inspection | 5/4/2018 | 5/4/2018 | 5/4/2018 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Footing | 12/20/2017 | 12/21/2017 | 12/21/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Cassandra Hessing need si report for final.
|
Issue PAID IN FULL permit | | | 11/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/24/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 10/6/2017 | 10/6/2017 | 11/24/2017 | | DEFR |
Brian McGowan
|
|
|
Helical Piers - need soils report
|
Telephone call | | | 11/24/2017 | | DONE |
|
|
|
called Cassandra to let know permit is ready and how muich is owed-also we need the RP-left message on her phone
|
Case Summary (BLD) | | | 11/24/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/24/2017 | | 11/24/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2017 | | DONE |
|
|
|
need RP
|
Routing - PUBLIC WORKS | 11/21/2017 | | 11/21/2017 | | PASS |
Jason C. Taylor
|
|
|
Geotech report is acceptable for required design criteria. JCT
|
Plan resubmittals received | | | 11/9/2017 | | DONE |
|
|
|
One copy of Geotechnical Engineering Evaluation taken to Brian Mc
|
Routing - PLAN CHECK | 10/6/2017 | | 10/6/2017 | | FAIL |
Brian McGowan
|
|
|
Need a soils report
|
Plan resubmittals received | | | 10/2/2017 | | DONE |
|
|
|
resubmittals recieved-instl guide for a different product from 1st submittal, fnd calcs, eng drawings-took to Brian McGowan
|
Routing Walk-In (BLD) | 9/27/2017 | 9/27/2017 | 9/27/2017 | P | FAIL |
Brian McGowan
|
|
|
Need soils report
|
1st review completed | | | 9/27/2017 | | FAIL |
Brian McGowan
|
|
|
Need soils report
|
Routing - PLAN CHECK | 9/27/2017 | | 9/27/2017 | | FAIL |
Brian McGowan
|
|
|
Need soils report
|
Application received | | 9/27/2017 | | | |
|
|
|
|