FIRE-Final Inspection | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | FAIL |
Troy Cobbley
|
|
|
Called contact number and left message that I would be there in 10 to 15. Went to the project site and could not make contact. Tenant was locked. No inspection performed.
Christi Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/5/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/28/2017 | 9/28/2017 | 10/3/2017 | | PASS |
Carl Westfall
|
|
|
(Oct 3 - 5 days)
|
Routing - PLAN CHECK | 9/29/2017 | | 10/3/2017 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 10/3/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/3/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/3/2017 | | DONE |
|
|
|
|
Telephone call | | | 10/3/2017 | | DONE |
|
|
|
Left a message for Christi informing her that this permit is ready and that one of us would go over the required inspections when she comes in ..
|
Plan resubmittals received | | | 10/2/2017 | | DONE |
|
|
|
Christi brought in resubmittals-changing direction of the doors to dressing room-took to Carl W
|
Routing - PUBLIC WORKS | | | 9/29/2017 | | PASS |
|
|
|
|
Routing - Addressing | 9/28/2017 | | 9/29/2017 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/28/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/28/2017 | | DONE |
|
|
|
|
Intake Approval | | | 9/27/2017 | | PASS |
|
|
|
per CJW
|
Application received | | 9/27/2017 | | | |
|
|
|
|