First Notice | 4/11/2018 | 4/11/2018 | 4/18/2018 | | DONE |
Jim Sly
|
|
|
This permit finaled on the web by Scott Campbell
|
BLD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Jim Sly
|
|
|
Contacts are either Don Rye or Jay Hintze Phone #: ###-#### Inspection requested via web by Scott Campbell
|
DOC - Permit Finaled | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarm, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
|
Zoning Approval | 4/3/2018 | 4/3/2018 | 4/3/2018 | | PASS |
Katelyn Menuge
|
|
|
|
PubWorks Occupancy Approval | 3/26/2018 | 3/26/2018 | 3/26/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Framing/Rough-in | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PASS |
Jim Sly
|
|
|
- Duke Phone #: ###-####
|
BLD-Wall Bracing | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PASS |
Jim Sly
|
|
|
shear- Duke Phone #: ###-####
|
BLD-Conference | 1/22/2018 | 1/22/2018 | 1/23/2018 | P | DONE |
Jim Sly
|
|
|
Duke Phone #: ###-####
|
BLD-Other | 12/20/2017 | 12/21/2017 | 12/21/2017 | A | PASS |
Jim Sly
|
|
|
Hole - Duke Phone #: ###-#### Holes for P/T 6x8 columns.
|
BLD-Conference | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | DONE |
Jim Sly
|
|
|
btwn 8-10 // Duke Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/4/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 12/4/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/24/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 10/18/2017 | 10/18/2017 | 11/24/2017 | | PASS |
Carl D Madsen
|
|
|
Quality Electric
|
Routing - PLAN CHECK | 11/10/2017 | | 11/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 11/10/2017 | | 11/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2017 | | DONE |
Christina Prado
|
|
|
Need:
ACHD - met
Revised Value - met
GC form - met
|
Routing - Design Review | 11/10/2017 | | 11/20/2017 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - FIRE | 11/10/2017 | 11/10/2017 | 11/14/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Route to Impact Fee Review | 11/9/2017 | 11/12/2017 | 11/9/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 11/9/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/18/2017 | | 11/9/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 10/18/2017 | | 11/9/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING Land Div | 10/18/2017 | | 11/3/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Drainage | 10/19/2017 | | 11/1/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 10/19/2017 | | 10/27/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 10/19/2017 | | 10/25/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing - FIRE | 10/18/2017 | 10/18/2017 | 10/20/2017 | | FAIL |
Scott Arellano
|
|
|
Attached review comments to case and emailed architect
|
Routing - Erosion and Sediment | 10/18/2017 | | 10/20/2017 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2017 | | 10/19/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 10/18/2017 | | 10/19/2017 | | PASS |
David Moser
|
|
|
Planning approval as per DRH and current planning not required.
|
Routing PW Sewer Rating | 10/19/2017 | | 10/19/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 10/18/2017 | | 10/18/2017 | | FAIL |
Katelyn Menuge
|
|
|
Corrections required, DR Appeal Period Ends October 23rd
|
Intake Approval | | | 10/18/2017 | | PASS |
|
|
|
|
Routing - Addressing | 10/18/2017 | | 10/18/2017 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 10/13/2017 | | FAIL |
|
|
|
Please provide the following items. Pre-Screen 10/13/17
Provide a soils and geotechnical report for the drainage report. The drainage report indicates a referenced geotechnical report but it is not for this property.
Site specific fire flow letter.
Design review approval letter.
Building code analysis on a cover sheet. No Building code analysis has been provided
Vicinity map
Indicate Fire Hydrants
Show current Parking
|
Intake Approval | | | 10/10/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please complete and upload the 502 checklist. All required documents shall be uploaded. No pre screen can occur at this time as submittal is not complete.
|
Application received | | | 9/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 29 2017 8:16AM
|