BLD-Final | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Sly
|
|
|
Bob Phone #: ###-####8 Blower door 2.6
|
DOC - Permit Finaled | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | PASS |
Jim Sly
|
|
|
|
Plan Modification Accepted | | | 7/2/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 7/2/2018 | | 7/2/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Conference | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | DONE |
Jim Sly
|
|
|
Bob Phone #: ###-####
|
BLD-Energy code compliance | 3/30/2018 | 3/30/2018 | 4/2/2018 | P | PASS |
Jim Sly
|
|
|
Bob Phone #: ###-####
|
BLD-Energy code compliance | 3/7/2018 | 3/8/2018 | 3/8/2018 | A | PART |
Jim Sly
|
|
|
Bob Phone #: ###-#### Foam/seal is in.
|
BLD-Framing/Rough-in | 3/7/2018 | 3/8/2018 | 3/8/2018 | A | PASS |
Jim Sly
|
|
|
Bob Phone #: ###-####
|
BLD-Wall Bracing | 1/30/2018 | 1/31/2018 | 1/31/2018 | P | PASS |
Jim Sly
|
|
|
BOB Phone #: ###-####
|
BLD-Foundation | 11/21/2017 | 11/22/2017 | 11/22/2017 | P | PART |
Mike Jordan
|
|
|
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Footing | 11/21/2017 | 11/21/2017 | 11/21/2017 | P | PASS |
Jim Sly
|
|
|
Alvorez 965 6103
|
BLD-Footing | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
Jim Sly
|
|
|
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
Issue PAID IN FULL permit | | | 11/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/20/2017 | | DONE |
|
|
|
|
Telephone call | | | 11/17/2017 | | DONE |
|
|
|
Left a message for Hans informing him that there is still over 8 thousand dollars in fees that needs to be paid before the permits can be issued
|
OVERRIDE | | | 11/16/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 11/16/2017 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 10/31/2017 | | 11/16/2017 | | DONE |
Michael Hanson
|
|
|
10/20 sfd L1 ePlan. 1st review complete. Returned to applicant, structural and energy deficiencies. MDH
|
Routing - PLAN CHECK | 11/8/2017 | | 11/16/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 11/8/2017 | | FAIL |
Michael Hanson
|
|
|
Returned to applicant. Structural and energy deficiencies. MDH
|
Routing - PLAN CHECK | 10/9/2017 | | 11/8/2017 | | FAIL |
Brian McGowan
|
|
|
Missing structural information and inaccurate energy numbers (insulation values didn't match). MDH
|
Routing - MECHANICAL | 10/9/2017 | | 10/12/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/9/2017 | 10/12/2017 | 10/10/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/9/2017 | | 10/10/2017 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 10/9/2017 | | 10/10/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan assigned to (BJM) | 10/9/2017 | 10/9/2017 | 10/9/2017 | | DEFR |
Brian McGowan
|
|
|
10/20 sfd L1 ePlan
|
Routing - Addressing | 10/9/2017 | | 10/9/2017 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/4/2017 | | FAIL |
|
|
|
Please upload plans in the "Landscape" format in the horizontal position.
|
Application received | | | 9/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 29 2017 1:27PM
|