First Notice | | 3/25/2018 | 3/20/2018 | | DONE |
|
|
|
This permit finaled on the web by Garrett Bailey
|
BLD-Final | 3/14/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
FIRE-Final Inspection | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection complete.
|
Permanent Occupancy | | | 3/15/2018 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 3/4/2018 | 3/5/2018 | 3/5/2018 | A | PASS |
Jim Storey
|
|
|
Please call 30 min. ahead of inspection. Phone #: ###-#### Inspection requested via web by Garrett Bailey
|
BLD-Framing/Rough-in | 1/10/2018 | 1/10/2018 | 1/11/2018 | P | PASS |
Dave Hannah
|
|
|
Garett Phone #: ###-####
|
BLD-Framing/Rough-in | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Dave Hannah
|
|
|
Garrett-please call 30 minutes prior for access Phone #: ###-####
|
Print Occupancy Form | | | 12/20/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/20/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/7/2017 | 12/7/2017 | 12/18/2017 | | PASS |
Javier Guzman
|
|
|
Plan Mod Idaho Scientific - Suite 402 ePlan, pend PW Envior
|
Routing PW Environmental | 12/8/2017 | | 12/18/2017 | | PASS |
Rick Christenson
|
|
|
PLAN MOD
|
Permit Ready to Issue | | | 12/18/2017 | | DONE |
|
|
|
NEED
GC FORM
REVISED CERT
|
Routing - PLAN CHECK | 12/8/2017 | | 12/9/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 12/8/2017 | | 12/8/2017 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING WITH PLAN MOD
|
Plan Modification Accepted | | | 12/7/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod to eliminate the proposed rest room w/shower and replace it with an enlarged conference room
|
Plan assigned to (JG) | 10/31/2017 | 10/31/2017 | 11/15/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 11/06 L1 Idaho Scientific TI ePlan
|
Routing - PLAN CHECK | 11/15/2017 | | 11/15/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/15/2017 | | DONE |
|
|
|
NEED
GC FORM
REVISED CERT
|
Route to Impact Fee Review | 11/13/2017 | 11/16/2017 | 11/14/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 10/31/2017 | | 11/13/2017 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 11/13/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 10/31/2017 | | 11/3/2017 | | PASS |
Rick Christenson
|
|
|
|
Intake Approval | | | 10/31/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 10/31/2017 | | 10/31/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/31/2017 | | 10/31/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 10/4/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 4 2017 5:00PM
|