BLD-Final | 5/23/2018 | 5/23/2018 | 5/23/2018 | A | PASS |
Brandon Shaw
|
|
|
Melissa will be here to inspect grade this morning. Phone #: ###-#### Inspection requested via web by Weston Wagner
|
DOC - Permit Finaled | 5/23/2018 | 5/23/2018 | 5/23/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/23/2018 | 5/23/2018 | 5/23/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.4
|
PubWorks Occupancy Approval | 5/23/2018 | 5/23/2018 | 5/23/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 5/17/2018 | 5/21/2018 | 5/21/2018 | A | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Final | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | NR |
Brandon Shaw
|
|
|
|
BLD-Other | 3/5/2018 | 3/5/2018 | 3/5/2018 | P | PASS |
Brandon Shaw
|
|
|
Rollo-soffit Phone #: ###-####
|
BLD-Energy code compliance | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
BLD-Framing/Rough-in | 2/20/2018 | 2/20/2018 | 2/20/2018 | A | PASS |
Brandon Shaw
|
|
|
|
BLD-Foundation | 12/19/2017 | 12/19/2017 | 12/19/2017 | P | CANC |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 12/13/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
Frost protection required
|
PubWorks Subgrade Approval | 12/13/2017 | 12/13/2017 | 12/13/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Inspection Record Card- Bld | | | 11/27/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/27/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/27/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/22/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 11/22/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2017 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 11/15/2017 | | 11/21/2017 | | DONE |
Michael Hanson
|
|
|
11/09 sfd L2 ePlan - 1st review complete Sent to BJM for final review
|
Routing - PLAN CHECK | 10/23/2017 | | 11/21/2017 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 11/17/2017 | | DONE |
Michael Hanson
|
|
|
Sent to BJM for final review
|
Routing PW Grading-Hillside | 10/23/2017 | | 10/30/2017 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - FIRE | 10/23/2017 | 10/23/2017 | 10/25/2017 | | PASS |
Erika Akin
|
|
|
Plans were reviewed for FD access, availability of hydrants and defensible space.
|
Routing - MECHANICAL | 10/23/2017 | | 10/25/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/23/2017 | 10/26/2017 | 10/24/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 10/23/2017 | | 10/24/2017 | | PASS |
Doug Chausow
|
|
|
|
Plan assigned to (BJM) | 10/23/2017 | 10/23/2017 | 10/23/2017 | | DEFR |
Brian McGowan
|
|
|
11/9 sfd L2 ePlan
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/23/2017 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2017 | | 10/23/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 10/23/2017 | | 10/23/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved.
|
Routing - PLANNING | 10/23/2017 | | 10/23/2017 | | PASS |
Jeff Lowe
|
|
|
|
Application received | | | 10/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 5 2017 4:15PM
|