Plan assigned to (JAR) | 6/5/2018 | 6/5/2018 | 6/5/2018 | | CANC |
Julie Romig
|
|
|
Plan mod for Fire, need to submit FIR application, Plan Mod cancelled
|
CHANGE STATUS TO (ISS) | | | 6/5/2018 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/9/2018 | 4/11/2018 | 4/11/2018 | P | NR |
Jim Sly
|
|
|
Curtis Phone #: ###-#### Need Electr. and Fire Finals.
|
FIRE-Final Inspection | 4/9/2018 | 4/11/2018 | 4/11/2018 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was just to meet/provide a correction notice for the existing deficient fire alarm system. It appears that the owner is going to move in the direction of an upgrade agreement. I discussed with Curtis the need to final all of the fire sprinkler permits, and go through the life safety items such as the emergency lights, exit signs....ect.
Curtis Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
Jim Sly
|
|
|
Curtis Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | PART |
Jim Sly
|
|
|
Chris Phone #: ###-#### Select rooms.
|
BLD-Framing/Rough-in | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | PART |
Jim Sly
|
|
|
Chris Phone #: ###-#### Select walls......OK.
|
FIRE-Final Inspection | 2/27/2018 | 2/28/2018 | 2/28/2018 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was actually a conference. I noted that the electrical engineer shows two strobes in remodeled rooms but there is no notification elsewhere in the store. Plans may need modified to delete these devices. I noted that a FIR permit will be requierd for the two new duct smoke detectors for units 10 and 12. I will need emergency lighting provided in the pass of egress from the remodeled areas and all existing emergency fixtures functional. There is still one fire sprinkler permit for phase 1 that has not been finaled yet.
Chris Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/20/2018 | 2/20/2018 | 2/21/2018 | P | PASS |
Jim Sly
|
|
|
Curtis Phone #: ###-####
|
BLD-Framing/Rough-in | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | PART |
Jim Sly
|
|
|
Curtis Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/22/2018 | 1/22/2018 | 1/23/2018 | P | PASS |
Jim Sly
|
|
|
Curtis-partial Phone #: ###-####
|
BLD-Framing/Rough-in | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PART |
Jim Sly
|
|
|
Curtis Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/28/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/28/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 11/1/2017 | 11/1/2017 | 12/18/2017 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 2nd Comp - L2 Target Remodel ePlan
|
Routing - PLAN CHECK | 12/18/2017 | | 12/18/2017 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 12/18/2017 | | 12/18/2017 | | PASS |
Julie Romig
|
|
|
3rd Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/18/2017 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED CERT
|
Routing Off Site - STRUCTURAL | 12/13/2017 | | 12/16/2017 | | FAIL |
Julie Romig
|
|
|
2nd Review
|
Routing - PLAN CHECK | 12/13/2017 | | 12/14/2017 | | PASS |
Julie Romig
|
|
|
|
Route to Impact Fee Review | 11/22/2017 | 11/25/2017 | 11/24/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - STRUCTURAL | 11/1/2017 | | 11/22/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
1st review completed | | | 11/22/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 11/1/2017 | | 11/22/2017 | | FAIL |
Julie Romig
|
|
|
Need stamp/signature on all architectural plans.
|
Routing - FIRE | 11/1/2017 | 11/1/2017 | 11/7/2017 | | PASS |
Erika Akin
|
|
|
Attached review comments to case
|
Routing - MECHANICAL | 11/1/2017 | | 11/2/2017 | | PASS |
Troy James
|
|
|
Passed per ePlanReview
|
Routing - PLUMBING | 11/1/2017 | | 11/2/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 11/1/2017 | | 11/1/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/1/2017 | | 11/1/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 11/1/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 11/1/2017 | | 11/1/2017 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00263
|
Intake Approval | | | 10/24/2017 | | FAIL |
Rob Patrick
|
|
|
10-24-17...Please submit dwgs as per the City of Boise naming standards, which can be found in the ePlanReview instructions at the City of Boise website. Use the link User Guide and go to Electronic Plan Submittal Standards.
|
Intake Approval | | | 10/9/2017 | | FAIL |
Rob Patrick
|
|
|
|
Application received | | | 10/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 6 2017 10:31AM
|