Third Notice | | 4/13/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19 with first follow up letter
|
First Follow up | | | 5/6/2019 | | DONE |
|
|
|
|
Print Statement | | | 4/16/2019 | | DONE |
|
|
|
|
Third Notice | | 3/16/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4/11
|
Third Notice | | 2/12/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12-19
|
Second Notice | | 1/18/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
First Notice | | 12/28/2018 | 1/8/2019 | | DONE |
|
|
|
mailed 1-11-19
|
BLD-Final | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. OK for perm occ.
|
Permanent Occupancy | | | 12/18/2018 | | DONE |
|
|
|
|
BLD-Final | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | NR |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Needs both mech. permits finaled first.
|
BLD-Final | 11/14/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. OK for temp occ. Will be ok for perm occ. once trades sign perm.
|
FIRE-Final Inspection | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Tony Phone #: ###-####
|
Temporary Occupancy | 11/15/2018 | 2/13/2019 | 11/15/2018 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 11/13/2018 | 11/14/2018 | 11/14/2018 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire alarm and fire sprinkler permit is addressed.
Tony Phone #: ###-####
|
BLD-Final | 11/14/2018 | 11/14/2018 | 11/14/2018 | A | FAIL |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Provide code compliant hardware on west stair.
|
FIRE-Conference | 11/7/2018 | 11/7/2018 | 11/7/2018 | P | DONE |
Troy Cobbley
|
|
|
I verified exit light and emergency light function
|
Zoning Approval | 11/1/2018 | 11/1/2018 | 11/1/2018 | | PASS |
Katelyn Menuge
|
|
|
|
PubWorks Occupancy Approval | 11/1/2018 | 11/1/2018 | 11/1/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Ceiling Grid Inspection | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Mike Jordan
|
|
|
Ceiling grid for soffits in ware house ok.
|
BLD-Ceiling Grid Inspection | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | CANC |
Mike Jordan
|
|
|
Jose Phone #: ###-####.
|
BLD-Ceiling Grid Inspection | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PASS |
Jim Storey
|
|
|
Jose Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. 1st. Floor only ok, pending sprinkler rough in.
|
BLD-Ceiling Grid Inspection | 9/25/2018 | 9/26/2018 | 9/27/2018 | A | CANC |
Mike Jordan
|
|
|
Jose Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/26/2018 | 9/26/2018 | 9/27/2018 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Other | 8/6/2018 | 8/7/2018 | 8/7/2018 | A | CANC |
Mike Jordan
|
|
|
Jose-plenum wall Phone #: ###-####
|
BLD-Energy code compliance | 8/2/2018 | 8/2/2018 | 8/2/2018 | P | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. 2nd.floor ok.
|
BLD-Energy code compliance | 7/30/2018 | 7/31/2018 | 7/31/2018 | A | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Exterior walls, north of gridline 2 only, 1st. floor.
|
BLD-Framing/Rough-in | 7/31/2018 | 7/31/2018 | 7/31/2018 | A | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Interior steel stud framed walls, 1st. and 2nd. floors north of gridline 2. pending plumbing rough in inspection.
|
BLD-Framing/Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Interior steel stud framed walls from gridlines 2 to 5 ok. Pending plumbing rough in inspection. Also noted that a select number of the interior full height walls are to be plenum walls. Electrical and plumbing inspectors were notified, as there are additional requirements.
|
BLD-Framing/Rough-in | 6/22/2018 | 6/25/2018 | 6/26/2018 | A | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Exterior steel stud columns ok.
|
BLD-Footing | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Interior column pad footings and exterior perimter footings. Pending special inspection.
|
Issue PAID IN FULL permit | | | 1/30/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/30/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 11/8/2017 | 11/8/2017 | 1/26/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 2nd Rec'd 01/17 - 502 Episciences
|
Routing - PLAN CHECK | 1/26/2018 | | 1/26/2018 | | PASS |
Julie Romig
|
|
|
3rd Review - Routed to Design Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/26/2018 | | DONE |
|
|
|
email permit to macyl@mcalvain.com
NEED RP -met
GC FORM -met
REVISED VALUE -met
ACHD -met
|
Routing - Design Review | 1/25/2018 | | 1/25/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 1/17/2018 | | 1/22/2018 | | PASS |
Julie Romig
|
|
|
2nd Review - pending Structural and Design Review approval
|
Routing Off Site - STRUCTURAL | 1/17/2018 | | 1/22/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing - PUBLIC WORKS | 1/17/2018 | | 1/19/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Drainage | 1/17/2018 | | 1/19/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 1/17/2018 | | 1/18/2018 | | PASS |
Bill VanDegrift
|
|
|
1) vent all traps
2) provide cleanouts per ISPC
3) additional cross connection protection may be required
4) 1/4" per foot grade on 3" and smaller waste piping
5) roof drainage system must be installed per ISPC. May be exterior downspouts.
|
Routing - Design Review | 1/17/2018 | | 1/17/2018 | | FAIL |
Katelyn Menuge
|
|
|
Landscape and light pole modifications required.
|
Route to Impact Fee Review | 1/8/2018 | 1/11/2018 | 1/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/8/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 11/8/2017 | | 1/8/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLANNING | 11/8/2017 | | 1/8/2018 | | PASS |
Julie Romig
|
|
|
No Review required per Susan Riggs in ePlanReview
|
Routing PW Sewer Design | 11/9/2017 | | 1/8/2018 | | PASS |
Mike Sheppard
|
|
|
|
Routing Off Site - STRUCTURAL | 11/8/2017 | | 11/27/2017 | | FAIL |
Julie Romig
|
|
|
|
Meeting | | | 11/16/2017 | | DONE |
|
|
|
Appendix J taken to Brain Murphy
|
Routing - MECHANICAL | 11/8/2017 | | 11/15/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 11/8/2017 | | 11/15/2017 | | FAIL |
Bill VanDegrift
|
|
|
change marks
1) provide rain water system design
2) provide a 4" drain to accept the discharge of the 1 1/2" R.P.
red lines
1) vent all floor drains
2) do not install a combination waste and vent system, vent all fixtures.
|
Routing - FIRE | 11/8/2017 | 11/8/2017 | 11/14/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing PW Environmental | 11/9/2017 | | 11/14/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 11/9/2017 | | 11/9/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 11/8/2017 | | 11/9/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/8/2017 | | 11/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 11/8/2017 | | 11/9/2017 | | PASS |
Michael Zawacki
|
|
|
Needs RP
|
Routing - Design Review | 11/8/2017 | | 11/9/2017 | | FAIL |
Katelyn Menuge
|
|
|
Landscape and lighting modifications required.
|
Intake Approval | | | 11/8/2017 | | PASS |
|
|
|
|
Intake Approval | | | 10/10/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
• Structural calculations stamped and signed by an Idaho licensed engineer.
• Please provide the missing specification book or clarify the specifications are incorporated within building plans
• Please provide owners signature and name of person who completed the form #310
• Please provide a Shallow Injection Well Inventory form from the Idaho Department of Water Resources available at: http://www.idwr.idaho.gov/wells/shallow-injection-wells.html
• Please have the provided ESC Narrative for this specific project signed by a plan designer certified by Boise City.
• Please provide the missing Recorded document (with instrument number) for all new and existing sewer easements
• Uploaded ESC Plans must be prepared and signed by a plan designer certified by Boise City.
• Please show location of the Portable fire extinguisher locations (checklist indicates this is a shell exception but the plans show this is going to be built out)
• Please provide a Commissioning Plan printed on the plans per 2012 IECC, you can also include a separate attached document. Form #308 IECC System Commissioning Agencies can be found at this link: http://pds.cityofboise.org/home/documents/apps/300/# (For new mechanical systems combined capacity 480,000 Btu/h or greater)
|
Application received | | | 10/9/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 9 2017 3:00PM
|
Routing - PLANNING Land Div | 11/8/2017 | | | | |
Todd Tucker
|
|
|
|
Routing PW Drainage | 11/9/2017 | | | | FAIL |
Brian Murphy
|
|
|
APDEX J AND PERC TEST
|