BLD-Final | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Jim Sly
|
|
|
Garage code 1331 Phone #: ###-#### Inspection requested via web by Andy Thompson
|
DOC - Permit Finaled | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson. Moved to pm.
|
BLD-Energy code compliance | 1/1/2018 | 1/3/2018 | 1/3/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 12/29/2017 | 12/29/2017 | 12/29/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
Plan Modification Accepted | | | 12/27/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 12/27/2017 | | 12/27/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 12/13/2017 | 12/13/2017 | 12/13/2017 | A | PASS |
Jim Sly
|
|
|
call on your way buddy so I can make sure I have the approved prints on site! I had new ones printed for you cause the originals were commandeered by the foundation crew apparently. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Wall Bracing | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | NR |
Mike Jordan
|
|
|
Andy is super awesome. Phone #: ###-#### Inspection requested via web by Andy Thompson. No approved plans on site.
|
BLD-Foundation | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PART |
Mike Jordan
|
|
|
11- Jose Phone #: ###-####
|
BLD-Footing | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 11/17/2017 | 11/20/2017 | 11/20/2017 | A | NR |
Mike Jordan
|
|
|
around 1pm please // Jose Phone #: ###-####. Rescheduled for pm inspection. Needs to have city approved plans on site.
|
BLD-Footing | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | NR |
Mike Jordan
|
|
|
Andy Phone #: ###-####
|
OVERRIDE | | | 11/17/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/17/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/2017 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 11/3/2017 | | 11/17/2017 | | DONE |
Michael Hanson
|
|
|
10/27 sfd L1 ePlan - 1st review complete. Returned to applicant. Wall bracing, foundation, and roof/floor framing deficiences. MDH
|
Routing - PLAN CHECK | 11/15/2017 | | 11/17/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 11/17/2017 | | 11/17/2017 | | PASS |
Beverly Mountain
|
|
|
|
Plan Reviewer's activity | | | 11/17/2017 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 11/17/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/9/2017 | | 11/15/2017 | | FAIL |
Brian McGowan
|
|
|
Returned to applicant. Did not satisfy to code the original deficiencies. MDH
|
Routing - Addressing | 11/14/2017 | | 11/14/2017 | | PASS |
Doug Chausow
|
|
|
|
1st review completed | | | 11/9/2017 | | FAIL |
Michael Hanson
|
|
|
Returned to applicant. Wall bracing, foundation, and roof/floor framing deficiences. MDH
|
Routing - PLAN CHECK | 10/16/2017 | | 11/9/2017 | | FAIL |
Brian McGowan
|
|
|
Returned to applicant. Wall bracing, foundation, and roof/floor framing deficiences. MDH
|
Routing - MECHANICAL | 10/16/2017 | | 10/18/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/16/2017 | 10/19/2017 | 10/17/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 10/16/2017 | 10/16/2017 | 10/16/2017 | | DEFR |
Brian McGowan
|
|
|
10/27 sfd L1 ePlan
|
Routing - PLANNING | 10/16/2017 | | 10/16/2017 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 10/16/2017 | | 10/16/2017 | | FAIL |
Doug Chausow
|
|
|
Plat has not been recorded with the County yet - the address is a temp address for electric and sewer, it is not a buildable parcel yet.
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/16/2017 | | PASS |
|
|
|
Pre Brent Moore, Subdivision has been recorded.
|
Intake Approval | | | 10/13/2017 | | FAIL |
|
|
|
Per Planning and zoning, the subdivision needs to be recorded prior to submitting for the building permit. (SUB17-00019)
|
Intake Approval | | | 10/10/2017 | | FAIL |
|
|
|
Needs to wait for SUB16-00038 for valid parcel, prescriptive for engery complaince needs to be on plans not in a single document, need insulation types and needs to show attic access location.
|
Application received | | | 10/9/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 9 2017 4:48PM
|
Routing - PUBLIC WORKS | 10/16/2017 | | | | FAIL |
|
|
|
FAIL DUE TO ADDRESSING ISSUES.
|