BLD-Final | 2/20/2019 | 2/21/2019 | 2/21/2019 | A | PASS |
Brandon Shaw
|
|
|
garage code 4646 Phone #: ###-#### Inspection requested via web by Chris Laraway
|
DOC - Permit Finaled | 2/21/2019 | 2/21/2019 | 2/21/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 2/21/2019 | 2/21/2019 | 2/21/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.9
|
BLD-Final | 2/18/2019 | 2/19/2019 | 2/19/2019 | A | FAIL |
Mike Jordan
|
|
|
Garage Code 4646. Thank you, Phone #: ###-#### Inspection requested via web by Chris Laraway. Glazing at mid landing of stairs is required to be tempered. Provide the blower door test results and post or the 3rd party airseal report. Correction notice posted.
|
Fees Due Hold | 2/19/2019 | 2/19/2019 | 2/19/2019 | | DONE |
Rita DeYoung
|
|
|
Fees owed on SWR. See Rita, Angela or Morgan
|
BLD-Aging Inspection | 8/1/2018 | 8/1/2018 | 8/1/2018 | | CANC |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 7/31/2018 | 7/31/2018 | 8/1/2018 | | PASS |
Mike Jordan
|
|
|
|
BLD-Wall cover | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | DONE |
Jim Storey
|
|
|
FYI, Momentum provided 3rd party inspection of insulation. Phone #: ###-#### Inspection requested via web by Chris Larawaycovered check at final .
|
BLD-Energy code compliance | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Mike Jordan
|
|
|
foam seal ; 3 shear hold down points in west wall. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Wall Bracing | 2/23/2018 | 2/26/2018 | 2/26/2018 | A | PASS |
Mike Jordan
|
|
|
Mr Jordan, Please call 30 min prior to arrival on site so I may meet with you on the corrections made. Thank you ~Chris Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Wall Bracing | 1/29/2018 | 1/31/2018 | 1/31/2018 | A | FAIL |
Mike Jordan
|
|
|
Framer is on site. Phone #: ###-#### Inspection requested via web by Chris Laraway. Install all mising hold downs on first floor, install missing floor to floor strap on 2nd. floor. Provide portal frame in back or engineering. Provide the wall bracing on garage wall. Correction notice issued. ok to tyvek.
|
Plan Modification Accepted | | | 1/23/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/23/2018 | | 1/23/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | PART |
Mike Jordan
|
|
|
Ready at 1:30 - James Phone #: ###-####
|
BLD-Footing | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PART |
Mike Jordan
|
|
|
late am please// James Phone #: ###-####
|
Inspection Record Card- Bld | | | 11/29/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/29/2017 | | DONE |
|
|
|
|
Telephone call | | | 11/27/2017 | | DONE |
|
|
|
emailed Chris Laraway need to pay impact fees to issue permit and release approved plans.
|
OVERRIDE | | | 11/24/2017 | | |
|
|
|
|
Plan Reviewer's activity | | | 11/24/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2017 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 11/8/2017 | | 11/24/2017 | | DONE |
Michael Hanson
|
|
|
11/1 sfd L1 ePlan - 1st review complete RTA wall bracing deficiencies.
|
Routing - PLAN CHECK | 10/19/2017 | | 11/24/2017 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 11/15/2017 | | FAIL |
Michael Hanson
|
|
|
Returned to applicant. Wall bracing deficiencies.
|
Route to Impact Fee Review | 10/19/2017 | 10/22/2017 | 10/20/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 10/20/2017 | | 10/20/2017 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 10/19/2017 | | 10/20/2017 | | FAIL |
Troy James
|
|
|
Emailed correction to TML
|
Routing - PLANNING | 10/19/2017 | | 10/20/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 10/19/2017 | | 10/20/2017 | | PASS |
Doug Chausow
|
|
|
|
Plan assigned to (BJM) | 10/19/2017 | 10/19/2017 | 10/19/2017 | | DEFR |
Brian McGowan
|
|
|
11/1 sfd L1 ePlan
|
Routing - PUBLIC WORKS | 10/19/2017 | | 10/19/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/19/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/19/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/19/2017 | | PASS |
|
|
|
|
Intake Approval | | | 10/12/2017 | | FAIL |
|
|
|
Site plans needs to be of whole parcel.
Crawl vents on foundation plan or details of a condition crawl space.
Stair section needs details of treads and risers.
|
Intake Approval | | | 10/12/2017 | | FAIL |
|
|
|
Per resubmittals standards all files must use the Exact same file name as the original drawing.
|
Application received | | | 10/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 11 2017 4:54PM
|