BLD-Final | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 10/29/2018 | 11/1/2018 | 11/1/2018 | A | NR |
Brandon Shaw
|
|
|
Need ELE final
|
BLD-Blower Door Test Results | 10/29/2018 | 11/1/2018 | 10/31/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.7
|
BLD-Energy code compliance | 8/16/2018 | 8/20/2018 | 8/20/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 8/15/2018 | 8/16/2018 | 8/16/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall cover | 7/24/2018 | 7/27/2018 | 7/27/2018 | A | PASS |
Brandon Shaw
|
|
|
Shear // Rudy Phone #: ###-####
|
BLD-Foundation | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 11/9/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/9/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/9/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/8/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 11/2/2017 | 11/2/2017 | 11/8/2017 | | PASS |
Josh Bogle
|
|
|
1st done - need engineered or larger footings
|
Routing - PUBLIC WORKS | 10/16/2017 | | 11/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLAN CHECK | 11/8/2017 | | 11/8/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Meeting | | | 11/8/2017 | | DONE |
|
|
|
emailed Josh B
PW has not signed off yet
|
Permit Ready to Issue | | | 11/8/2017 | | DONE |
|
|
|
met
|
1st review completed | | | 11/6/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/16/2017 | | 11/6/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 10/16/2017 | | 11/6/2017 | | PASS |
Susan Riggs
|
|
|
PLANS RED-LINED. THE DECK CAN'T ENCROACH INTO THE 5' SIDE YARD SETBACK.
|
Routing - MECHANICAL | 10/16/2017 | | 10/19/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 10/16/2017 | 10/19/2017 | 10/17/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 10/16/2017 | 10/16/2017 | 10/16/2017 | | DEFR |
Brian McGowan
|
|
|
10/27 sfd L1 ePlan
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/16/2017 | | PASS |
|
|
|
|
Routing - Addressing | 10/16/2017 | | 10/16/2017 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 10/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 13 2017 10:39AM
|
Intake Approval | | | 10/13/2017 | | FAIL |
|
|
|
All plans must be uploaded in landscape format.
|