Print Statement | | | 3/29/2018 | | DONE |
|
|
|
|
First Notice | | 3/5/2018 | 3/15/2018 | | DONE |
|
|
|
mailed 3-16-18
|
Permanent Occupancy | | | 2/23/2018 | | DONE |
|
|
|
|
BLD-Final | 2/22/2018 | 2/22/2018 | 2/22/2018 | P | PASS |
Jim Sly
|
|
|
Zack Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 2/14/2018 | 2/20/2018 | 2/21/2018 | P | NR |
Jim Sly
|
|
|
zack Phone #: ###-####-would like as late as possible as the fire lifesafety is early pm today Need CDHD
|
FIRE-Final Inspection | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Zack Phone #: ###-####-please do as early PM as possible as the building final is late pm today
|
FIRE-Final Inspection | 2/14/2018 | 2/20/2018 | 2/20/2018 | A | FAIL |
Troy Cobbley
|
|
|
Two exit signs failed to function
Zach Phone #: ###-####
|
Plan assigned to (JG) | 2/12/2018 | 2/12/2018 | 2/14/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod Copenross Growlers ePlan
|
Routing - PLAN CHECK | 2/14/2018 | | 2/14/2018 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 2/14/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 2/14/2018 | | DONE |
|
|
|
emailed permit to customr to sign
|
(F) Reprint permit | | | 2/14/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 2/12/2018 | 2/15/2018 | 2/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 2/12/2018 | | DONE |
|
|
|
Plan mod workflow started for - The building area calculations were adjusted and the code analysis, egress plan, and area plans were updated accordingly.
|
FIRE-Final Inspection | 2/7/2018 | 2/9/2018 | 2/9/2018 | A | FAIL |
Troy Cobbley
|
|
|
Provide panic hardware at the Seating Area exit door as per plans, provide occupant load sign, repair exit signs and emergency lights/exit discharge lights, mount the fire extinguisher, provide ADA hardware on the back Storage Room door.
|
BLD-Framing/Rough-in | 1/26/2018 | 1/29/2018 | 1/29/2018 | A | PASS |
Jim Sly
|
|
|
Zach Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/6/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/6/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 11/15/2017 | 11/15/2017 | 12/4/2017 | | PASS |
Javier Guzman
|
|
|
11/28 L2 Copenross Growlers ePlan
|
Routing - PLAN CHECK | 11/15/2017 | | 12/4/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 12/4/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/4/2017 | | DONE |
|
|
|
Need
Cert of Value -met
GC Form - met
|
Routing Off Site - C.D.H | 11/15/2017 | | 12/2/2017 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by Central District Health Department Dinko Miljkovic
|
Routing - PLUMBING | 11/15/2017 | | 12/2/2017 | | PASS |
Bill VanDegrift
|
|
|
signed off in ePlan by Plumbing Bill Vandegrift
|
Routing PW Environmental | 11/15/2017 | | 11/21/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 11/15/2017 | 11/15/2017 | 11/20/2017 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Intake Approval | | | 11/15/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 11/15/2017 | | 11/15/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/15/2017 | | 11/15/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 11/15/2017 | | 11/15/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - MECHANICAL | 11/15/2017 | | 11/15/2017 | | PASS |
Troy James
|
|
|
Talked to mechanical engineer about interlocking hood with RTU's
|
Application received | | | 10/16/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 16 2017 9:20AM
|
Intake Approval | | | 10/16/2017 | | FAIL |
Rob Patrick
|
|
|
Jeremy, Please provide the following:
1. Zoning Certificate Required for the changes to the parking area and addition of outdoor seating. You can contact Sarah Schafer at ###-#### for further direction. Thank you.
|