Second Notice | | 4/20/2018 | 4/23/2018 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
First Notice | 3/20/2018 | 3/20/2018 | 4/10/2018 | | DONE |
Dave Hannah
|
|
|
mailed 4-11-18
|
Permanent Occupancy | | | 4/2/2018 | | DONE |
|
|
|
|
BLD-Final | 3/19/2018 | 3/20/2018 | 3/20/2018 | A | PASS |
Dave Hannah
|
|
|
Stan Phone #: ###-####
|
DOC - Permit Finaled | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | NR |
Dave Hannah
|
|
|
Stan Phone #: ###-#### needs elec final first
|
FIRE-Final Inspection | 3/9/2018 | 3/9/2018 | 3/9/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete (FIR17-00658), fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
|
BLD-Ceiling Grid Inspection | 2/20/2018 | 2/20/2018 | 2/21/2018 | P | PEND |
Dave Hannah
|
|
|
Kelly Phone #: ###-#### ok after elec oks
|
Issue PAID IN FULL permit | | | 12/4/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/16/2017 | 10/16/2017 | 11/27/2017 | | PASS |
Carl Westfall
|
|
|
f (Oct 27 - 10 days) Paper - St. Luke's
|
Routing - FIRE | 11/22/2017 | | 11/27/2017 | | PASS |
Erika Akin
|
|
|
Attached comments to case and plans
|
1st review completed | | | 11/27/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/27/2017 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/27/2017 | | DONE |
Christina Prado
|
|
|
Need:
GC Form - MET
REvised Certificate of Value - MET
|
Telephone call | | | 11/27/2017 | | DONE |
|
|
|
Spoke with Brenda informing her that this permit is ready and that the GC will need to fill out the 302 and 306 forms so that we can add in the rest of the fees
|
Routing - PLUMBING | 11/21/2017 | | 11/22/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Street Lights | 11/21/2017 | | 11/21/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - PUBLIC WORKS | 11/20/2017 | | 11/21/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 11/21/2017 | | 11/21/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Addressing | 11/20/2017 | | 11/20/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLAN CHECK | 10/16/2017 | | 11/20/2017 | | PASS |
Carl Westfall
|
|
|
This is a paper plan. It was not routed as it should have been when it was submitted. Much processing time was lost because of this. It wasn't routed until after the IBC plan review.
|
(F) Reprint permit | | | 10/16/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/16/2017 | | PASS |
|
|
|
per CJW
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2017 | | DONE |
|
|
|
|
Application received | | 10/16/2017 | | | |
|
|
|
|