BLD-Final | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/11/2018 | 6/11/2018 | 6/11/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 5.7
|
BLD-Energy code compliance | 3/8/2018 | 3/8/2018 | 3/8/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to cover
Fire/area seperation wall- Pass
|
BLD-Framing/Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 2/13/2018 | 2/13/2018 | 2/13/2018 | A | PASS |
Jim Sly
|
|
|
Shear inspect Inspection requested via web by Erby Gonzales Exterior straps and Nailing ....OK.
|
BLD-Foundation | 12/19/2017 | 12/20/2017 | 12/20/2017 | A | PASS |
Brandon Shaw
|
|
|
wall// Doug Phone #: ###-####
|
BLD-Footing | 12/18/2017 | 12/18/2017 | 12/18/2017 | P | PASS |
Brandon Shaw
|
|
|
Doug Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/5/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/27/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 11/27/2017 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 10/18/2017 | 10/18/2017 | 11/19/2017 | | DONE |
Brian McGowan
|
|
|
11/6 Townhome L2 ePlan
|
Routing - PLAN CHECK | 10/18/2017 | | 11/19/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 11/19/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLANNING | 10/18/2017 | | 10/23/2017 | | PASS |
Katelyn Menuge
|
|
|
SUB16-00047 and DRH17-00261
|
Routing - MECHANICAL | 10/18/2017 | | 10/20/2017 | | PASS |
Troy James
|
|
|
|
Routing PW Flood Plain | 10/19/2017 | | 10/20/2017 | | PASS |
Jason C. Taylor
|
|
|
Project has approved LOMR. Jason Taylor ###-####
|
Route to Impact Fee Review | 10/18/2017 | 10/21/2017 | 10/19/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 10/18/2017 | | 10/18/2017 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/18/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/18/2017 | | PASS |
|
|
|
|
Application received | | 10/16/2017 | | | |
|
|
|
|
Application received | | 10/16/2017 | | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2017 | | | | |
|
|
|
|