Permanent Occupancy | | | 5/10/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/7/2018 | | DONE |
|
|
|
|
First Notice | 3/23/2018 | 3/23/2018 | 4/10/2018 | | DONE |
Mike Jordan
|
|
|
mailed 4-11-18
|
BLD-Final | 3/22/2018 | 3/23/2018 | 3/23/2018 | P | PASS |
Mike Jordan
|
|
|
Please contact JP ###-#### Phone #: ###-#### Inspection requested via web by Mattie Botero
|
DOC - Permit Finaled | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Jim Page
|
|
|
Only fire sprinkler in tenant space is in gas closet (gas closet is existing, room appears to be rated with a self closing door, tanks are sucure), no other fire sprinklers, no fire alarms, fire extinguishers are in place and will be tagged with current inspection tags. Final life fire safety inspection for area of work complete.
|
BLD-Ceiling Grid Inspection | 3/19/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Mike Jordan
|
|
|
Please contact JP at ###-#### Phone #: ###-#### Inspection requested via web by Mattie Botero.
|
BLD-Framing/Rough-in | 2/20/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mattie Botero. Interior wood framed walls and soffit for new entry and admin. area.
|
BLD-Framing/Rough-in | 2/16/2018 | 2/20/2018 | 2/20/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mattie Botero Inspection cancelled from web by: Scott Hawker
|
BLD-Ceiling Grid Inspection | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mattie Botero
|
BLD-Framing/Rough-in | 1/4/2018 | 1/5/2018 | 1/5/2018 | A | PART |
Mike Jordan
|
|
|
Contact is JP ###-#### Phone #: ###-#### Inspection requested via web by Mattie Botero. Interior wood framed walls and soffits for phase 2 ok, pend. electrical rough in inspection.
|
BLD-Ceiling Grid Inspection | 12/19/2017 | 12/20/2017 | 12/20/2017 | A | PASS |
Mike Jordan
|
|
|
Please contact Scott in advance. ###-####. Please enter the building through the door on the South end. Thanks. Phone #: ###-#### Inspection requested via web by Mattie Botero
|
BLD-Ceiling Grid Inspection | 12/18/2017 | 12/19/2017 | 12/19/2017 | A | NR |
Mike Jordan
|
|
|
Please call Scott in advance. ###-####. Enter building through the door on the North side. Thank you. Phone #: ###-#### Inspection requested via web by Mattie Botero. Need electrical roughin inspection. Electrical was not ready.
|
BLD-Other | 11/28/2017 | 11/29/2017 | 11/28/2017 | A | PASS |
Mike Jordan
|
|
|
Insulation inspection. Contact is JP ###-#### Phone #: ###-#### Inspection requested via web by Mattie Botero
|
BLD-Energy code compliance | 11/28/2017 | 11/28/2017 | 11/28/2017 | P | PASS |
Mike Jordan
|
|
|
Insulation inspection. Contact is JP ###-#### Phone #: ###-#### Inspection requested via web by Mattie Botero
|
BLD-Framing/Rough-in | 11/17/2017 | 11/20/2017 | 11/20/2017 | A | PASS |
Mike Jordan
|
|
|
J.P is contact. Phone #: ###-#### Inspection requested via web by Mattie Botero. Interior wood framed wals and soffits for phase 1 ok.
|
BLD-Framing/Rough-in | 11/13/2017 | 11/14/2017 | 11/14/2017 | A | NR |
Mike Jordan
|
|
|
Jp Phone #: ###-####. Needs plumbing rough in inspection. Needs to pull electrical permit and rough in inspection.
|
Issue PAID IN FULL permit | | | 11/3/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/3/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/3/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/3/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 10/23/2017 | 10/23/2017 | 11/1/2017 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 2nd Rec'd 10/31 - L2 Times Square Dental
|
Routing - PLAN CHECK | 10/31/2017 | | 11/1/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/1/2017 | | DONE |
|
|
|
Need
GC - met
rev cert of val - met
|
Route to Impact Fee Review | 10/28/2017 | 10/31/2017 | 10/30/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/28/2017 | | DONE |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 10/23/2017 | | 10/28/2017 | | FAIL |
Julie Romig
|
|
|
See Plan Review Report in ePlanReview
|
Routing - FIRE | 10/23/2017 | 10/23/2017 | 10/27/2017 | | PASS |
Erika Akin
|
|
|
Attached review comments to case
|
Routing PW Environmental | 10/23/2017 | | 10/27/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 10/23/2017 | | 10/26/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 10/23/2017 | | 10/24/2017 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required
|
Routing - Addressing | 10/23/2017 | | 10/23/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2017 | | 10/23/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 10/23/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Rob approved pre screen
|
Intake Approval | | | 10/18/2017 | | FAIL |
Rob Patrick
|
|
|
Jay, Please provide the following:
1. Stamped and "Signed" dwgs. Mechanical and Plumbing dwgs are stamped but not signed.
Thank you!
|
Application received | | | 10/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2017 1:37PM
|