BLD-Final | 11/29/2018 | 11/29/2018 | 11/29/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Paul Fedorchuk
|
DOC - Permit Finaled | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall needs code complant window in master bedroom
|
BLD-Blower Door Test Results | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall 4.33
|
BLD-Energy code compliance | 9/21/2018 | 9/24/2018 | 9/24/2018 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 9/19/2018 | 9/20/2018 | 9/20/2018 | P | PEND |
Brandon Shaw
|
|
|
2 ply box truss to bear down to foundation... Fire blocking needed at drop ceiling... Strap needed at bearing wall, up stairs bnus room... See red paint OK to Insulate
|
BLD-Wall Bracing | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Brandon Shaw
|
|
|
Shear // Eber Phone #: ###-####
|
BLD-Aging Inspection | 8/9/2018 | 8/9/2018 | 8/9/2018 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Wall Bracing | 8/8/2018 | 8/8/2018 | 8/8/2018 | A | DEFR |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 8/8/2018 | 8/8/2018 | 8/8/2018 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Foundation | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
(F) Reprint permit | | | 12/28/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 12/27/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 12/27/2017 | 12/27/2017 | 12/27/2017 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/27/2017 | | 12/27/2017 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLANNING | 12/27/2017 | | 12/27/2017 | | PASS |
Susan Riggs
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/27/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 12/27/2017 | | DONE |
|
|
|
DO NOT ISSUE. PLAN MOD
|
Plan Modification Accepted | | | 12/19/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod to mirror plan, door showing on the plan is on wrong side. Route to Planning & Building
|
Issue PAID IN FULL permit | | | 11/9/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/9/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/8/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 11/6/2017 | 11/6/2017 | 11/8/2017 | | PASS |
Josh Bogle
|
|
|
1st done - footings inadequate
|
Routing - PLAN CHECK | 11/8/2017 | | 11/8/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 11/8/2017 | | DONE |
|
|
|
met
|
1st review completed | | | 11/7/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/18/2017 | | 11/7/2017 | | FAIL |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 10/18/2017 | | 10/26/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/18/2017 | 10/21/2017 | 10/19/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 10/18/2017 | 10/18/2017 | 10/18/2017 | | DEFR |
Brian McGowan
|
|
|
10/31 sfd L1 ePlan
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/18/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/18/2017 | | PASS |
|
|
|
|
Routing - PLANNING | 10/18/2017 | | 10/18/2017 | | PASS |
Susan Riggs
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2017 | | 10/18/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 10/18/2017 | | 10/18/2017 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 10/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2017 4:17PM
|