Permit Information
Permit NumberBLD17-03765
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 6165 E HOOTOWL DR
Project NameTablerock HN 84-1
Customer Number 
ePlanReviewYes
Description
HILLSIDE, WUI ZONE "A", CLASS "A" ROOF REQUIRED. Permit for the construction of a new 3,406 sq. ft., two story (first story 2,546 sq. ft., second story 860 sq. ft.) single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately 287 sq. ft. of covered patio/porch and a 1,046 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. ***BJM***

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/11/20186/12/20186/12/2018APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Weston Wagner
DOC - Permit Finaled6/12/20186/12/20186/12/2018PPASS
DetailsBrandon Shaw
BLD-Final6/8/20186/8/20186/8/2018ACANC
DetailsBrandon Shaw
Phone #: ###-#### >> Inspection requested via web by Weston Wagner Inspection cancelled from web by: Weston Wagner
PubWorks Occupancy Approval6/8/20186/8/20186/8/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Energy code compliance3/6/20183/7/20183/7/2018APASS
DetailsBrandon Shaw
rolo Phone #: ###-####
BLD-Other3/2/20183/2/20183/2/2018PPASS
DetailsBrandon Shaw
soffit // Rolo Phone #: ###-####
BLD-Other2/28/20183/1/20183/1/2018AFAIL
DetailsBrandon Shaw
Not complete
BLD-Framing/Rough-in2/26/20182/26/20182/26/2018PPASS
DetailsBrandon Shaw
OK to insulate
BLD-Wall cover2/7/20182/8/20182/8/2018APASS
DetailsBrandon Shaw
BLD-Foundation12/13/201712/13/201712/13/2017PPASS
DetailsBrandon Shaw
Work in progress

Frost protection required
BLD-Footing12/6/201712/7/201712/7/2017APASS
DetailsBrandon Shaw
Thermal protection provided

Work in progress
BLD-Conference12/6/201712/7/201712/6/2017ACANC
DetailsBrandon Shaw
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
PubWorks Subgrade Approval12/5/201712/5/201712/5/2017 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
OVERRIDE  11/16/2017  
Plan assigned to (BJM)10/18/201710/18/201711/16/2017 DONE
DetailsBrian McGowan
11/6 sfd L2 ePlan
PLANS/APPL TAKEN TO FRONT DESK  11/16/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  11/16/2017 DONE
Issue PAID IN FULL permit  11/16/2017 DONE
Inspection Record Card- Bld  11/16/2017 DONE
1st review completed  11/15/2017 DONE
DetailsBrian McGowan
Routing - Erosion and Sediment10/18/2017 11/15/2017 PASS
DetailsAndy J. Long
ESC plan approved. Valid RP and PD designated.
Routing - PLAN CHECK10/18/2017 11/15/2017 PASS
DetailsBrian McGowan
Routing - MECHANICAL10/18/2017 10/26/2017 PASS
DetailsTroy James
Routing PW Grading-Hillside10/19/2017 10/24/2017 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
Routing - FIRE10/18/201710/18/201710/20/2017 PASS
DetailsErika Akin
Plans were reviewed for FD access, availability of hydrants and defensible space.
Route to Impact Fee Review10/18/201710/21/201710/19/2017 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - Addressing10/18/2017 10/19/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/18/2017 10/19/2017 PASS
DetailsRachael Beierle
Application received  10/18/2017 DONE
Application submitted via PDS Online on Oct 18 2017 10:31AM
Plans ACCEPTED BY PLAN TECH  10/18/2017 DONE
Recd Pcfee & Taken To Pln CK  10/18/2017 DONE
Intake Approval  10/18/2017 PASS
Routing - PLANNING10/18/2017 10/18/2017 PASS
DetailsJeff Lowe