BLD-Final | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Jim Sly
|
|
|
Russ Phone #: ###-####
|
DOC - Permit Finaled | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 8/23/2018 | 8/24/2018 | 8/24/2018 | A | PART |
Tony Young
|
|
|
Rusty Phone #: ###-####,, need trades
|
BLD-Energy code compliance | 5/8/2018 | 5/8/2018 | 5/8/2018 | P | PASS |
Tony Young
|
|
|
Rusty Phone #: ###-####
|
BLD-Framing/Rough-in | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | PASS |
Jim Sly
|
|
|
Rusty Phone #: ###-####
|
BLD-Framing/Rough-in | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | NR |
Tony Young
|
|
|
Rusty Phone #: ###-####, see paint marks,, don't insulate
|
BLD-Wall Bracing | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | PART |
Tony Young
|
|
|
Rusty Phone #: ###-####,, exterior ok
|
Plan Modification Accepted | | | 4/17/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 4/17/2018 | | 4/17/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 4/13/2018 | 4/13/2018 | 4/13/2018 | P | NR |
Tony Young
|
|
|
Rusty Phone #: ###-####
|
BLD-Wall Bracing | 4/12/2018 | 4/13/2018 | 4/13/2018 | A | FAIL |
Brandon Shaw
|
|
|
1) See PHF detail for header nailing patern and nail size 2) Edge vanf field nailing to be as per plans 3) blocking required at shear panels Correction notice left See red paint
|
BLD-Wall Bracing | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | CANC |
Tony Young
|
|
|
Shear // Rusty Phone #: ###-####
|
BLD-Wall Bracing | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | NR |
Tony Young
|
|
|
Shear // Rusty Phone #: ###-####,, late am
|
BLD-Wall Bracing | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | NR |
Tony Young
|
|
|
Shear // Rusty Phone #: ###-####
|
BLD-Foundation | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | PART |
Tony Young
|
|
|
Mike Phone #: ###-####,, work in progress ok
|
BLD-Footing | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | DONE |
Tony Young
|
|
|
Mike Phone #: ###-####,, done
|
BLD-Footing | 1/22/2018 | 1/23/2018 | 1/23/2018 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/8/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/4/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 10/23/2017 | 10/23/2017 | 1/4/2018 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 12/30/2017 | | 1/4/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/4/2018 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLANNING | 1/4/2018 | | 1/4/2018 | | PASS |
Brent Moore
|
|
|
|
Permit Ready to Issue | | | 1/4/2018 | | DONE |
|
|
|
Met
|
Plan Reviewer's activity | | | 12/20/2017 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 12/18/2017 | | 12/18/2017 | | FAIL |
Brian McGowan
|
|
|
Living space is cantilevered over the side setback.
|
Plan Reviewer's activity | | | 12/11/2017 | | DONE |
Rob Patrick
|
|
|
Needs Tall Wall engineering
|
Plan Reviewer's activity | | | 12/5/2017 | | FAIL |
Rob Patrick
|
|
|
Need depth of existing pool and depth of new foundations
|
Routing - PLAN CHECK | 11/27/2017 | | 11/27/2017 | | FAIL |
Rob Patrick
|
|
|
|
1st review completed | | | 11/16/2017 | | FAIL |
Rob Patrick
|
|
|
|
Plan Reviewer's activity | | | 11/16/2017 | | FAIL |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 10/23/2017 | | 11/16/2017 | | PASS |
Chad Schwendiman
|
|
|
Review completed by 413
|
Route to Impact Fee Review | 10/23/2017 | 10/26/2017 | 10/24/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 10/23/2017 | 10/23/2017 | 10/23/2017 | | DEFR |
Brian McGowan
|
|
|
11/3 sfd L1 ePlan
|
Routing - PLANNING | 10/23/2017 | | 10/23/2017 | | FAIL |
Brent Moore
|
|
|
2nd Story encroaches into north 5' side yard setback and covered patio encroaches into south 5' side yard setback.
|
Routing - Addressing | 10/23/2017 | | 10/23/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2017 | | 10/23/2017 | | PASS |
Morgan Webb
|
|
|
MUST SUPPLY OWN SERVICE LINE
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/23/2017 | | PASS |
|
|
|
|
Application received | | | 10/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 20 2017 9:05AM
|
Intake Approval | | | 10/20/2017 | | FAIL |
|
|
|
All plans must be uploaded in “Landscape” format in the horizontal position.
|