BLD-Final | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 4/21/2018 | 4/24/2018 | 4/24/2018 | A | NR |
Mike Jordan
|
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Everything ok. Needs mech final first prior to sign off.
|
BLD-Energy code compliance | 3/8/2018 | 3/8/2018 | 3/8/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Energy code compliance | 3/6/2018 | 3/7/2018 | 3/7/2018 | P | FAIL |
Brandon Shaw
|
|
|
See framing notes- add additional fasteners to BG2 (2 ply) Truss-
|
BLD-Framing/Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Ok to insulate. provide additional fasteners at bottom chord og BG2 in garage.
|
BLD-Wall Bracing | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Mike Jordan
|
|
|
Fortino Phone #: ###-####
|
BLD-Foundation | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 1/24/2018 | 1/25/2018 | 1/25/2018 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####. No one on site. No foundation forms erected.
|
BLD-Foundation | 1/23/2018 | 1/24/2018 | 1/24/2018 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 1/22/2018 | 1/23/2018 | 1/23/2018 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####. No one on site. No stemwall forms erected.
|
BLD-Footing | 1/19/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 1/18/2018 | 1/19/2018 | 1/19/2018 | P | FAIL |
Mike Jordan
|
|
|
Dane Phone #: ###-####. Contractor to compact pitrun. Appears to be uncontrolled fill.
|
Issue PAID IN FULL permit | | | 12/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/12/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 12/7/2017 | | |
|
|
|
|
Plan assigned to (M_H) | 11/16/2017 | | 12/7/2017 | | DONE |
Michael Hanson
|
|
|
11/09 sfd L1 ePlan - 1st review completed. RTA - structural deficiences. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/7/2017 | | DONE |
|
|
|
Met
|
Routing - PLAN CHECK | 12/6/2017 | | 12/6/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/20/2017 | | 11/30/2017 | | FAIL |
Brian McGowan
|
|
|
RTA - Did not resolve wall bracing or framing changemark. MDH
|
Plan Reviewer's activity | | | 11/20/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/27/2017 | | 11/20/2017 | | FAIL |
Brian McGowan
|
|
|
RTA - Structural deficiences.
|
1st review completed | | | 11/17/2017 | | DONE |
Michael Hanson
|
|
|
Additional Footing, BWL clarification needed.
|
Routing - MECHANICAL | 11/6/2017 | | 11/6/2017 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 10/27/2017 | | 10/31/2017 | | FAIL |
Troy James
|
|
|
Emailed corrections to icon air
|
Route to Impact Fee Review | 10/27/2017 | 10/30/2017 | 10/30/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 10/27/2017 | 10/27/2017 | 10/27/2017 | | DEFR |
Brian McGowan
|
|
|
11/9 sfd L1 ePlan
|
Routing - PLANNING | 10/27/2017 | | 10/27/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 10/27/2017 | | 10/27/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 10/27/2017 | | 10/27/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/27/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/27/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/27/2017 | | PASS |
|
|
|
|
Application received | | | 10/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2017 3:18PM
|
Intake Approval | | | 10/24/2017 | | FAIL |
|
|
|
Need a REScheck or prescriptive method shown on plans.
|