First Notice | 10/30/2018 | 10/30/2018 | 11/7/2018 | | DONE |
Jim Storey
|
|
|
mailed 11-12
|
BLD-Final | 10/30/2018 | 10/30/2018 | 10/30/2018 | A | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 10/25/2018 | 10/26/2018 | 10/26/2018 | P | PART |
Jim Storey
|
|
|
Tim Phone #: ###-#### achd sign off/ letter aprovals engineer and si co.
|
PubWorks Occupancy Approval | 10/24/2018 | 10/24/2018 | 10/24/2018 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 10/8/2018 | 10/9/2018 | 10/9/2018 | A | PASS |
Jim Page
|
|
|
Bags have been removed from fire hydrants, final life fire safety inspection complete.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | FAIL |
Jim Page
|
|
|
Fire hydrants are bagged over by SUEZ due to payment issue, issue needs to be resolved before life fire safety inspection can be passed.
Tim Phone #: ###-####
|
Zoning Approval | 9/26/2018 | 9/26/2018 | 9/26/2018 | | PASS |
Katelyn Menuge
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/27/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/27/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/22/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 8/17/2018 | 8/17/2018 | 8/22/2018 | | PASS |
Carl Westfall
|
|
|
Plan Mod - Gowen Industrial Park - Warehouse Building A (plan intake approved and routed)
|
Routing PW Sewer Rating | 8/21/2018 | | 8/22/2018 | | PASS |
Rachael Beierle
|
|
|
ALL FIXTURES REMOVED. CREDITS AVAILABLE.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/22/2018 | | DONE |
|
|
|
PLAN MOD
|
Routing - PLAN CHECK | 8/20/2018 | | 8/21/2018 | | PASS |
Carl Westfall
|
|
|
Drawings uploaded by applicant. 2nd plan mod plan intake approved.
|
Routing - PLAN CHECK | 8/21/2018 | | 8/21/2018 | | PASS |
Carl Westfall
|
|
|
2nd plan mod review approved
|
Plan Modification Accepted | | | 8/17/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | P | PART |
Jim Storey
|
|
|
John Phone #: ###-####-only walls demising and fire riser room well as joists
|
CHANGE STATUS TO (ISS) | | | 7/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/4/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 3/27/2018 | 3/27/2018 | 4/4/2018 | | PASS |
Carl Westfall
|
|
|
x Gowan Industrial Park Plan Mod
|
Routing - PLAN CHECK | 3/27/2018 | | 4/4/2018 | | PASS |
Carl Westfall
|
|
|
1st plan mod approved
|
Plan Reviewer's activity | | | 4/4/2018 | | PASS |
|
|
|
1st plan mod approved
|
Permit Ready to Issue | | | 4/4/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
Plan Modification Accepted | | | 3/27/2018 | | DONE |
|
|
|
Remove 1 hour rarted ceiling access hatch
|
Inspection Record Card- Bld | | | 2/13/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/13/2018 | | DONE |
|
|
|
|
Telephone call | | | 2/6/2018 | | DONE |
|
|
|
CAN eamiled David Minegar that all project fees must be paid prior to issuance of permit.
|
OVERRIDE | | | 1/18/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 10/30/2017 | 10/30/2017 | 1/18/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Dec 1 - 25 days) (92 sheets) Gowan Industrial Park Building A
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/18/2018 | | DONE |
|
|
|
EMAIL DAVID MINEGAR at dminegar@laytonconstruction.com
MET
Need:
GC form
Revised value
|
Routing PW Street Lights | 1/17/2018 | | 1/18/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 1/17/2018 | | 1/17/2018 | | PASS |
Katelyn Menuge
|
|
|
Please remember to resolve your changemark. Delete it if it is on the most current version of a drawing.
|
Routing - PLAN CHECK | 1/16/2018 | | 1/17/2018 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 1/16/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/5/2018 | | 1/9/2018 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 1/9/2018 | | DONE |
|
|
|
|
Routing - Design Review | 1/8/2018 | | 1/8/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing PW Street Lights | 1/8/2018 | | 1/8/2018 | | FAIL |
Tom Marshall
|
|
|
|
Route to Impact Fee Review | 1/4/2018 | 1/7/2018 | 1/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals received | | | 1/5/2018 | | DONE |
|
|
|
Came in late on Friday. Routed early Monday morning.
|
1st review completed | | | 1/4/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/4/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/30/2017 | | 1/4/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing PW Street Lights | 10/30/2017 | | 12/19/2017 | | FAIL |
Tom Marshall
|
|
|
|
Routing - Erosion and Sediment | 11/20/2017 | | 11/20/2017 | | PASS |
Andy J. Long
|
|
|
Project scope under ESC17-01200 modified to cover Building A ESC coverage. Do not need to issue new ESC permit (ESC17-01510) with this building permit. Permit modification fee needs to be paid on ESC17-01200.
|
Routing PW Drainage | 11/15/2017 | | 11/17/2017 | | PASS |
Jason C. Taylor
|
|
|
Reassigned from Brian Murphy
|
Routing PW Drainage | 10/30/2017 | | 11/17/2017 | | PASS |
Brian Murphy
|
|
|
Drainage project approved under ODI 3663. Jason Taylor ###-####
|
Routing Off Site - STRUCTURAL | 10/30/2017 | | 11/10/2017 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing PW Environmental | 10/30/2017 | | 11/3/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - Erosion and Sediment | 10/30/2017 | | 11/2/2017 | | PASS |
Michael Zawacki
|
|
|
|
Routing - MECHANICAL | 10/30/2017 | | 11/2/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 10/30/2017 | | 11/1/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - FIRE | 10/30/2017 | 10/30/2017 | 10/31/2017 | | PASS |
Scott Arellano
|
|
|
Attached review comments to case
|
Routing PW Sewer Design | 10/30/2017 | | 10/31/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Solid Waste | 10/30/2017 | | 10/31/2017 | | PASS |
Evan Carpenter
|
|
|
|
Intake Approval | | | 10/30/2017 | | PASS |
|
|
|
|
Routing - PLANNING | 10/30/2017 | | 10/30/2017 | | PASS |
Leon Letson
|
|
|
|
Routing - Addressing | 10/30/2017 | | 10/30/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/30/2017 | | 10/30/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 10/30/2017 | | 10/30/2017 | | FAIL |
Katelyn Menuge
|
|
|
Corrections required and ROS shall be completed prior to building permit issuance.
|
Intake Approval | | | 10/26/2017 | | FAIL |
|
|
|
Form 31 needs to be signed by the EOR
Site and landscape plans are required
|
Application received | | | 10/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2017 4:01PM
|