BLD-Final | 11/12/2019 | 11/13/2019 | 11/13/2019 | P | DEFR |
Brandon Shaw
|
|
|
See previous enrty from PW...
|
DOC - Permit Finaled | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 11/7/2019 | 11/7/2019 | 11/7/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the retaining wall is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 10/30/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 10/25/2017 | 10/25/2017 | 10/30/2017 | | PASS |
Josh Bogle
|
|
|
retaining wall - Hillside - paper
|
Routing - PLAN CHECK | | | 10/30/2017 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLANNING | 10/27/2017 | | 10/30/2017 | | PASS |
Brent Moore
|
|
|
|
1st review completed | | | 10/30/2017 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 10/30/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2017 | | DONE |
Josh Bogle
|
|
|
ESc yes - Energy no
|
Routing - Erosion and Sediment | 10/30/2017 | | 10/30/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site prepararation inspection is required.
|
Permit Ready to Issue | | | 10/30/2017 | | DONE |
|
|
|
Need
RP
GC Form
Revised Cert of Value
|
Issue PAID IN FULL permit | | | 10/30/2017 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 10/25/2017 | | 10/27/2017 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
|
Routing - PUBLIC WORKS | 10/27/2017 | | 10/27/2017 | | PASS |
Morgan Webb
|
|
|
RETAINING WALL.NO SEWER
|
Routing - Addressing | 10/27/2017 | | 10/27/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/25/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/25/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/25/2017 | | DONE |
|
|
|
no fees paid at intake
|
Application received | | 10/25/2017 | | | |
|
|
|
|