BLD-Final | 1/23/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
DOC - Permit Finaled | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.6
|
BLD-Final | 1/17/2019 | 1/18/2019 | 1/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson. Provide handrail at main entry exterior stairs.
|
BLD-Energy code compliance | 11/1/2018 | 11/9/2018 | 11/8/2018 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Energy code compliance | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Other | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
Tony Young
|
|
|
We will have insulators on site today so that you can see the baffels we are installing. Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Conference | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
Tony Young
|
|
|
Insulators are onsite now so that you can see the baffels. Let me know when you will be there and I will meet you to discuss. Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Conference | 11/1/2018 | 11/1/2018 | 11/1/2018 | A | DEFR |
Tony Young
|
|
|
We will have insulators on site today so that you can see the baffels we are installing. Phone #: ###-#### Inspection requested via web by James Jackson,, not ready
|
BLD-Framing/Rough-in | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Framing/Rough-in | 10/25/2018 | 10/25/2018 | 10/25/2018 | P | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson,, correction posted,, strap beams/plates, add king studs per plan, fire blocks, seal plate at vac line, nail king studs into header layers, justify how the roof will be vented, fireblock stair run where no sheetrock will be on the underside, nail plywood by the top of stairs,, will need a level landing out exit door,, do not insulate
|
BLD-Wall Bracing | 10/5/2018 | 10/8/2018 | 10/8/2018 | A | PART |
Brandon Shaw
|
|
|
Work in progress- hold downs and floor to floor straps
|
BLD-Foundation | 8/31/2018 | 8/31/2018 | 8/31/2018 | P | PART |
Tony Young
|
|
|
gilber Phone #: ###-####,, work in progress,, needs rebar clearance to forms,, ok after fixes
|
BLD-Footing | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Dave Hannah
|
|
|
Gilbert Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/17/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/17/2018 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2018 | | DONE |
|
|
|
Spoke with Ryan informing him that this permit is going to expire in 11 days. he stated that they will pay for the permit next week
|
Expiration Notice | 3/30/2018 | 4/20/2018 | 3/30/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 11/29/2017 | | |
|
|
|
|
Plan assigned to (M_H) | 11/24/2017 | | 11/29/2017 | | DONE |
Michael Hanson
|
|
|
11/15 sfd L1 ePlan - 1st review complete. Sent to JAB. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 11/29/2017 | | DONE |
|
|
|
Met
|
1st review completed | | | 11/27/2017 | | DONE |
Michael Hanson
|
|
|
|
Plan Reviewer's activity | | | 11/27/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 11/2/2017 | | 11/27/2017 | | PASS |
Josh Bogle
|
|
|
|
Plan assigned to (BJM) | 11/2/2017 | 11/2/2017 | 11/24/2017 | | DEFR |
Brian McGowan
|
|
|
11/15 sfd L1 ePlan
|
Route to Impact Fee Review | 11/2/2017 | 11/5/2017 | 11/3/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 11/2/2017 | | 11/3/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 11/2/2017 | | 11/3/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/2/2017 | | 11/2/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 11/2/2017 | | 11/2/2017 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/2/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/2/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/2/2017 | | DONE |
|
|
|
|
Application received | | | 10/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 26 2017 10:28AM
|