BLD-Final | 4/17/2018 | 4/19/2018 | 4/19/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 4/17/2018 | 4/18/2018 | 4/17/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Energy code compliance | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Framing/Rough-in | 2/2/2018 | 2/5/2018 | 2/5/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Wall Bracing | 1/22/2018 | 1/23/2018 | 1/23/2018 | A | PASS |
Brandon Shaw
|
|
|
Ever Phone #: ###-####
|
BLD-Foundation | 12/11/2017 | 12/11/2017 | 12/11/2017 | P | PASS |
Brandon Shaw
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
Frost protection required
|
Issue PAID IN FULL permit | | | 11/29/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/29/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/28/2017 | | |
|
|
|
|
Plan assigned to (RDP) | 11/21/2017 | 11/21/2017 | 11/28/2017 | | DONE |
Rob Patrick
|
|
|
11/14 sfd L1 ePlan. 11/24/17 - emailed for clarification of hold-downs. 11/27/17 - Sent to Josh for review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2017 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 11/28/2017 | | DONE |
|
|
|
met
|
Plan Reviewer's activity | | | 11/27/2017 | | DONE |
Rob Patrick
|
|
|
|
1st review completed | | | 11/27/2017 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 11/1/2017 | | 11/27/2017 | | PASS |
Josh Bogle
|
|
|
|
Plan assigned to (BJM) | 11/1/2017 | 11/1/2017 | 11/21/2017 | | DEFR |
Brian McGowan
|
|
|
11/14 sfd L1 ePlan. 11-27-17 submitted to Josh for review.
|
Route to Impact Fee Review | 11/1/2017 | 11/4/2017 | 11/3/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 11/1/2017 | | 11/3/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 11/1/2017 | | 11/1/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 11/1/2017 | | 11/1/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/1/2017 | | 11/1/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/1/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/1/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/1/2017 | | DONE |
|
|
|
|
Application received | | | 10/31/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 31 2017 8:43AM
|