Permit Information
Permit NumberBLD17-04037
StatusFinaled
Name CORE BUILDING COMPANY
Site Address 5745 N FENWICK AVE
Project NameL3 B3 Millwell
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 1985 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 273 sq. ft. of covered patio/porch and a 697 sq. ft. attached garage per the approved plans. R-1C zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/19/20186/20/20186/20/2018APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter
DOC - Permit Finaled6/20/20186/20/20186/20/2018PPASS
DetailsTony Young
c of o issued
BLD-Wall Bracing4/12/20184/12/20184/12/2018PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, new framers to fix
BLD-Framing/Rough-in4/12/20184/12/20184/12/2018PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter
BLD-Energy code compliance4/11/20184/12/20184/12/2018APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter
BLD-Framing/Rough-in4/11/20184/12/20184/12/2018AFAIL
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, trusses braces still not nailed at 6' oc..
BLD-Wall Bracing4/11/20184/12/20184/12/2018AFAIL
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, still not per plan
BLD-Framing/Rough-in4/3/20184/3/20184/3/2018PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, ok to insulate,, see paint marks,, RE- NAIL ALL SHEAR/BRACING
BLD-Wall Bracing3/20/20183/21/20183/21/2018AFAIL
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, need to re-do
Plan Modification Accepted  3/20/2018 DONE
new manual j report
Routing - MECHANICAL3/20/2018 3/20/2018 PASS
DetailsTroy James
resubmitted manual j report
BLD-Footing12/11/201712/12/201712/12/2017APASS
DetailsBrandon Shaw
Work in progress

Frost protection required
OVERRIDE  12/5/2017  
Issue PAID IN FULL permit  12/5/2017 DONE
Inspection Record Card- Bld  12/5/2017 DONE
Plan assigned to (M_H)11/29/2017 12/5/2017 DONE
DetailsMichael Hanson
11/17 sfd L1 ePlan - 1st review completed. RTA - structural deficiencies. MDH
Routing - PLAN CHECK12/1/2017 12/5/2017 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  12/5/2017 DONE
DetailsMichael Hanson
Permit Ready to Issue  12/5/2017 DONE
met
Plan Reviewer's activity  11/30/2017 DONE
DetailsMichael Hanson
1st review completed  11/30/2017 FAIL
DetailsMichael Hanson
RTA - structural deficiencies. MDH
Routing - PLAN CHECK11/6/2017 11/30/2017 FAIL
DetailsBrian McGowan
Plan assigned to (BJM)11/6/201711/6/201711/29/2017 DEFR
DetailsBrian McGowan
11/17 sfd L1 ePlan
Route to Impact Fee Review11/6/201711/9/201711/7/2017 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL11/6/2017 11/7/2017 PASS
DetailsTroy James
Application received  11/6/2017 DONE
Application submitted via PDS Online on Nov 6 2017 12:55PM
Plans ACCEPTED BY PLAN TECH  11/6/2017 DONE
Intake Approval  11/6/2017 PASS
Recd Pcfee & Taken To Pln CK  11/6/2017 DONE
Routing - PLANNING11/6/2017 11/6/2017 PASS
DetailsJeff Lowe
Routing - Addressing11/6/2017 11/6/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS11/6/2017 11/6/2017 PASS
DetailsRachael Beierle