Third Notice | | 10/17/2018 | 10/31/2018 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
Third Notice | | 9/15/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
First Follow up | | | 10/12/2018 | | DONE |
|
|
|
|
Third Notice | | 8/13/2018 | 9/10/2018 | | DONE |
|
|
|
mailed 9-11-18
|
Third Notice | | 7/15/2018 | 8/8/2018 | | DONE |
|
|
|
mailed 8-10-18
|
Second Notice | | 6/21/2018 | 7/10/2018 | | DONE |
|
|
|
mailed 7-11-18
|
First Notice | | 6/11/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Permanent Occupancy | | | 6/1/2018 | | DONE |
|
|
|
|
BLD-Final | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Dave Hannah
|
|
|
Ken Phone #: ###-####
|
FIRE-Final Inspection | 5/22/2018 | 5/23/2018 | 5/23/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, fire alarm inspection is complete, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection for area of work complete.
Ken Storey Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/17/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Framing/Rough-in | 2/23/2018 | 2/26/2018 | 2/26/2018 | A | PASS |
Dave Hannah
|
|
|
Ken Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/21/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/21/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 12/16/2017 | 12/19/2017 | 12/19/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 12/19/2017 | | DONE |
|
|
|
MET
Need:
GC Form
Revised Cert of Value
|
Plan assigned to (JAR) | 11/9/2017 | 11/9/2017 | 12/16/2017 | | DONE |
Julie Romig
|
|
|
WGP2 - 1-Flr Rev Cycle (#103) ePlan
|
Routing - PLAN CHECK | 11/9/2017 | | 12/16/2017 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 12/16/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 11/9/2017 | | 11/15/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 11/9/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 11/9/2017 | | 11/9/2017 | | PASS |
Doug Chausow
|
|
|
Suite 103
|
Routing - PUBLIC WORKS | 11/9/2017 | | 11/9/2017 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Application received | | | 11/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2017 4:17PM
|