Third Notice | | 6/16/2018 | 7/10/2018 | | DONE |
|
|
|
mailed 7-11-18
|
Second Notice | | 5/21/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
First Notice | | 4/23/2018 | 5/11/2018 | | DONE |
|
|
|
mailed 5-14
|
BLD-Final | 4/11/2018 | 4/13/2018 | 4/13/2018 | A | PASS |
Jim Storey
|
|
|
Patrick Phone #: ###-#### fiaal ok no card on site
|
Permanent Occupancy | | | 4/13/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | PASS |
Jim Page
|
|
|
Previously noted items have been addressed, final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given until the permanant address is provided and the fire extinguisher is mounted with current tag as discussed.
Chris Phone #: ###-####
|
BLD-Final | 2/26/2018 | 2/26/2018 | 2/26/2018 | P | PART |
Jim Storey
|
|
|
Jason Phone #: ###-#### need address # and fire insp. per aproved plan
|
BLD-Framing/Rough-in | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Brandon Shaw
|
|
|
Thru beam at 2hr wall, fire caulking in place Thru Trusses at 2hr wall, packed with mineral wool and to be fire caulked
|
BLD-Conference | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Jim Storey
|
|
|
Jason Phone #: ###-#### soffits ok/2 hr fire sepetration as per aproved plans wip
|
Issue PAID IN FULL permit | | | 1/23/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/23/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 11/13/2017 | 11/13/2017 | 1/11/2018 | | PASS |
Carl Westfall
|
|
|
(1st done) (Dec 1 - 15 days) (19 sheets) Zeppole Bakery
|
Routing - PLAN CHECK | 1/10/2018 | | 1/11/2018 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2018 | | DONE |
|
|
|
Need
GC Form
Revised Cert of Value
|
Plan resubmittals received | | | 1/10/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/4/2018 | 1/7/2018 | 1/4/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 11/13/2017 | | 1/4/2018 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 1/4/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/4/2018 | | DONE |
|
|
|
|
Routing PW Environmental | 11/14/2017 | | 11/21/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 11/13/2017 | 11/13/2017 | 11/16/2017 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Erosion and Sediment | 11/13/2017 | | 11/16/2017 | | PASS |
Andy J. Long
|
|
|
No ESC permit required. No exterior disturbance, minimal saw cutting.
|
Routing - PUBLIC WORKS | 11/13/2017 | | 11/15/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 11/13/2017 | | 11/15/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 11/13/2017 | | 11/15/2017 | | PASS |
Daryl Spivey
|
|
|
|
Routing - PLANNING | 11/13/2017 | | 11/14/2017 | | PASS |
Cody Riddle
|
|
|
Approved as part of a use exception (CUP07-00117).
|
Routing - Addressing | 11/13/2017 | | 11/14/2017 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 11/13/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl M accepted pre screen CDH approval uploaded at submittal
|
Application received | | | 11/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2017 5:00PM
|