Third Notice | | 7/15/2018 | 7/13/2018 | | DONE |
|
|
|
This permit finaled on the web by Rob Maes
|
Second Notice | | 6/21/2018 | 7/10/2018 | | DONE |
|
|
|
mailed 7-11-18
|
First Notice | 5/29/2018 | 5/29/2018 | 6/11/2018 | | DONE |
Tony Young
|
|
|
mailed 6-12
|
BLD-Final | 5/29/2018 | 5/30/2018 | 5/29/2018 | A | PASS |
Tony Young
|
|
|
Pls contact Greg (Project Mgr) @ ###-#### if you have any questions. Thank you. Inspection requested via web by Rob Maes// the electrical permit was on the 1010 Washington address,, ok,, see ele18-00880
|
DOC - Permit Finaled | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Final | 5/25/2018 | 5/29/2018 | 5/29/2018 | A | NR |
Tony Young
|
|
|
Pls contact Greg (Project Mgr) @ ###-#### if you have any questions. Thank you. Inspection requested via web by Rob Maes,, still needs electrical permit and inspection,, recieved letter from structural engineer of ok on installation
|
BLD-Final | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | NR |
Tony Young
|
|
|
Please contact Greg Meyet @ ###-#### one hour prior to arrival. He will meet you on site. Thank you. Inspection requested via web by Rob Maes,, called.. no answer,, left messege.. no return call,, will need electrical permit and inspection,, need letter of ok as built from the structural engineer..
|
BLD-Final | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | NR |
Jim Sly
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Verified Electr. finaled. Told Bryce That he needs Special inspection of epoxy bolting ....before final.
|
BLD-Framing/Rough-in | 3/16/2018 | 3/21/2018 | 3/21/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Plan assigned to (JG) | 11/22/2017 | 11/22/2017 | 3/7/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/05 Boise High Solar Panels pend eng
|
Routing Off Site - STRUCTURAL | 3/6/2018 | | 3/7/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Dave Haugland
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/7/2018 | | DONE |
|
|
|
NEED
GC FORM - met
|
Issue PAID IN FULL permit | | | 3/7/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/22/2018 | | 3/5/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/22/2018 | | 2/24/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 2/7/2018 | | 2/20/2018 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by AHJ Engineers Dave Haugland
|
Routing - PLAN CHECK | 2/7/2018 | | 2/20/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Design Review | 2/7/2018 | | 2/7/2018 | | PASS |
Andrea Tuning
|
|
|
|
Plan Reviewer's activity | | | 1/30/2018 | | DONE |
Javier Guzman
|
|
|
No engineering calculation and No planning and zoning approval letter uploaded, please upload items requested from the panning & Zoning and the requested engineering calculations
|
Routing Off Site - STRUCTURAL | 1/22/2018 | | 1/27/2018 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by AHJ Engineers Dave Haugland
|
Routing - PLAN CHECK | 1/22/2018 | | 1/27/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 1/22/2018 | | 1/22/2018 | | FAIL |
Andrea Tuning
|
|
|
This request requires Design Review approval.
|
Route to Impact Fee Review | 12/7/2017 | 12/10/2017 | 12/8/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 12/7/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 11/22/2017 | | 12/7/2017 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by AHJ Engineers Dave Haugland
|
Routing - PLAN CHECK | 11/22/2017 | | 12/7/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - ELECTRICAL | 11/22/2017 | | 12/7/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 11/22/2017 | 11/22/2017 | 11/27/2017 | | PASS |
Scott Arellano
|
|
|
No separate comments attached to plans. The following items shall be field verified by the PDS/Fire & Electrical field inspectors.
IFC 605.11.1 Marking is required on interior and exterior direct-current (DC) conduit, enclosures, raceways, cable assemblies, junction boxes, combiner boxes and disconnects.
605.11.1.1 The materials used for marking shall be reflective, weather resistant and suitable for the environment.
605.11.1.2 The marking shall contain the words “WARNING: PHOTOVOLTAIC POWER SOURCE.”
605.11.1.3 The marking shall be placed adjacent to the main service disconnect in a location clearly visible from the location where the disconnect is operated.
605.11.1.4 Marking shall be placed on interior and exterior DC conduit, raceways, enclosures and cable assemblies every 10 feet , within 1 foot of turns or bends and within 1 foot above and below penetrations of roof/ceiling assemblies, walls or barriers.
|
Routing - PLANNING | 11/22/2017 | | 11/24/2017 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Design Review | 11/22/2017 | | 11/22/2017 | | FAIL |
Sarah Schafer
|
|
|
Planning approval required. Applicant's rep/contractor has been contacted. Further discussions will take place on 11/27/17.
|
Intake Approval | | | 11/22/2017 | | PASS |
|
|
|
|
Intake Approval | | | 11/14/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide the following and upload:
• Any items the checklist is requesting and applies to your project shall be uploaded, Incomplete submittals will not be accepted. Applicants with incomplete submittals must upload additional documents
• Please provide a cut sheet showing the listing for the sunshield awning
• Please provide details, listing, size and type of combiner box “JB-R”
• Please provide per snap n rack manufacturer’s specifications and shows its listed
• Please provide per snap n rack manufacturer’s specifications that show method of grounding and bonding of modules and arrays
• Please provide Snap N Rack Cut manufactures specifications and shows its listed
• Plans show Enphase S280 micro inverters but a spec sheet od Enphase IQ 6 was uploaded please revise plans to match uploaded micro inverters or provide Enphase S280 micro inverters manufactures specifications and shows its listed
|
Application received | | | 11/9/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 9 2017 8:25AM
|
Intake Approval | | | 11/9/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide the following and upload:
• Please provide a completed #520 PV Checklist found at our website at https://pds.cityofboise.org/media/466093/520-commercial-pv-solar-thermal-systems-submittal-checklist-final_9-25-17.pdf
• The checklist is not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed.
• Any items the checklist is requesting and applies to your project shall be uploaded, Incomplete submittals will not be accepted. Applicants with incomplete submittals must upload additional documents
• Any item on the checklist that only has a single box for checking that item shall be required
|