BLD-Final | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Mike Jordan
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
DOC - Permit Finaled | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 5/30/2018 | 5/30/2018 | 5/30/2018 | A | DONE |
Mike Jordan
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley. 3.98@50ach
|
BLD-Energy code compliance | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 3/7/2018 | 3/8/2018 | 3/8/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Framing/Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley. Complete lateral bracing on A04,A05 and A07 trusses. Roll block trusses A04 thru A07, south end and A08 on north end. Correction notice posted. ok to insulate.
|
BLD-Framing/Rough-in | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | NR |
Brandon Shaw
|
|
|
Need air seal
|
BLD-Wall Bracing | 2/12/2018 | 2/13/2018 | 2/13/2018 | A | PASS |
Mike Jordan
|
|
|
Gate Code: #9898 Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Wall Bracing | 2/8/2018 | 2/12/2018 | 2/12/2018 | A | NR |
Mike Jordan
|
|
|
Gate Code #9898 Phone #: ###-#### Inspection requested via web by Jessica Bradley. No approved plans on site.
|
BLD-Foundation | 12/31/2017 | 1/2/2018 | 1/2/2018 | P | PART |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 12/28/2017 | 12/29/2017 | 12/29/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
Issue PAID IN FULL permit | | | 12/28/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 12/20/2017 | | |
|
|
|
|
Routing - PLAN CHECK | 12/18/2017 | | 12/20/2017 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/20/2017 | | DONE |
|
|
|
Met
|
Plan assigned to (M_H) | 12/1/2017 | | 12/20/2017 | | DONE |
Michael Hanson
|
|
|
11/27 sfd L1 ePlan - plan is similar to 04098, 1st review completed. MDH
RTA - Failed structural spread footings, girder truss load path. MDH
|
Routing - PLAN CHECK | 11/14/2017 | | 12/18/2017 | | FAIL |
Brian McGowan
|
|
|
RTA - Failed structural spread footings, girder truss load path. MDH
|
Plan Reviewer's activity | | | 12/15/2017 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 12/7/2017 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (BJM) | 11/14/2017 | 11/14/2017 | 12/1/2017 | | DEFR |
Brian McGowan
|
|
|
11/27 sfd L1 ePlan
|
Routing - MECHANICAL | 11/14/2017 | | 11/16/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/14/2017 | 11/17/2017 | 11/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 11/14/2017 | | 11/14/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 11/14/2017 | | 11/14/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/14/2017 | | 11/14/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 11/14/2017 | | FAIL |
|
|
|
Application was the only item uploaded
|
Plans ACCEPTED BY PLAN TECH | | | 11/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/14/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/14/2017 | | DONE |
|
|
|
|
Application received | | | 11/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 13 2017 1:21PM
|