PubWorks Occupancy Approval | 1/8/2019 | 1/8/2019 | 1/8/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 12/17/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Mitchell
|
DOC - Permit Finaled | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 5/11/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Mitchell
|
BLD-Framing/Rough-in | 5/8/2018 | 5/8/2018 | 5/9/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Mitchell
|
BLD-Wall Bracing | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Mitchell
|
BLD-Framing/Rough-in | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Mitchelll,, walk through only
|
BLD-Wall cover | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PART |
Tony Young
|
|
|
2nd floor drywall Phone #: ###-#### Inspection requested via web by Nate Mitchell,, work in progress
|
BLD-Wall Bracing | 2/22/2018 | 2/22/2018 | 2/22/2018 | A | PART |
Tony Young
|
|
|
Firewall Sheetrock Phone #: ###-#### Inspection requested via web by Nate Mitchell,, need to nail off better,, then ok,, 1st floor of this building
|
BLD-Foundation | 1/17/2018 | 1/17/2018 | 1/18/2018 | P | PASS |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 1/16/2018 | 1/17/2018 | 1/17/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Mitchell
|
Issue PAID IN FULL permit | | | 1/3/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/3/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/29/2017 | | |
|
|
|
|
Routing - PLAN CHECK | 12/29/2017 | | 12/29/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/29/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/29/2017 | | DONE |
|
|
|
12 permits total
|
Plan assigned to (BJM) | 11/20/2017 | | 12/29/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete -12/6 townhomes L2 paper
|
Routing - PLAN CHECK | 12/19/2017 | | 12/27/2017 | | FAIL |
Brian McGowan
|
|
|
Structure did not match Architectural
|
Routing - Design Review | 12/19/2017 | | 12/20/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH17-00039.
|
Routing - MECHANICAL | 12/19/2017 | | 12/19/2017 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 12/6/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering as individual units required.
|
Routing - PLAN CHECK | | | 12/6/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering as individual units required.
|
Routing - MECHANICAL | 11/22/2017 | | 11/24/2017 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 11/21/2017 | | 11/22/2017 | | PASS |
Cody Riddle
|
|
|
|
Routing - Design Review | 11/22/2017 | | 11/22/2017 | | FAIL |
Sarah Schafer
|
|
|
The plans failed per the requirements of DRH17-00038. The side entry access to the unit adjacent to the parking area was not provided and the landscape plan shown on the cover sheet was not a detailed landscape plan nor did it match the plan in the DR file. Notes were made to the requirement for the entry and canopy on sheets A0.1, A03, A2.1 and A3.
|
Routing - Addressing | 11/20/2017 | | 11/21/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/20/2017 | | 11/21/2017 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 11/17/2017 | 11/20/2017 | 11/20/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 11/17/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/17/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/17/2017 | | PASS |
|
|
|
4 townhouses
BLD17-04203
BLD17-04204
BLD17-04205
BLD17-04206
|
Application received | | 11/17/2017 | | | |
|
|
|
|