BLD-Aging Inspection | 11/7/2018 | 11/7/2018 | 11/13/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 11/6/2018 | 11/6/2018 | 11/13/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Footing | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | PEND |
Tony Young
|
|
|
Footing inspection on piers Phone #: ###-#### Inspection requested via web by Cassandra Hessing,, needs special inspection,, pending report
|
OVERRIDE | | | 1/18/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 1/12/2018 | 1/12/2018 | 1/18/2018 | | PASS |
Josh Bogle
|
|
|
1st done - waiting on Geotech MOD
|
Inspection Record Card- Bld | | | 1/18/2018 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 1/18/2018 | | DONE |
Christina Prado
|
|
|
Called ABC to advise permit is ready, no fees due
|
CHANGE STATUS TO (ISS) | | | 1/18/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/18/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 1/18/2018 | | 1/18/2018 | | PASS |
Jason C. Taylor
|
|
|
New MTI Addendum #1 changing from helical anchors to push pins has been approved. JCT
|
Routing - PLAN CHECK | 1/18/2018 | | 1/18/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 1/18/2018 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE - Plan mod with no additional fees due, all requirements met
|
Plan Reviewer's activity | | | 1/16/2018 | | FAIL |
Josh Bogle
|
|
|
ran MTI report by JCT to see if addequate, no - JAB
|
Plan Modification Accepted | | | 1/12/2018 | | DONE |
|
|
|
plan changes-did walk in and sent to JAB
|
Issue PAID IN FULL permit | | | 12/22/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/29/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 11/22/2017 | 11/22/2017 | 11/29/2017 | | PASS |
Josh Bogle
|
|
|
1st done - Hillside, helical piers - need ES report, etc.
|
Routing - PLAN CHECK | 11/29/2017 | | 11/29/2017 | | PASS |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 11/28/2017 | | 11/29/2017 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Erosion and Sediment | 11/29/2017 | | 11/29/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Valid RP designated.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2017 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/29/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/29/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 11/29/2017 | | DONE |
|
|
|
met
|
Plan assigned to (JAB) Josh | 11/22/2017 | 11/22/2017 | 11/28/2017 | | PASS |
Josh Bogle
|
|
|
1st done - Hillside, helical piers - need ES report, etc.
|
Plan resubmittals received | | | 11/28/2017 | | DONE |
|
|
|
resubmittal received 1 set of materials and testing and ICC-ES Evaluations-took to JAB
|
Routing - PLAN CHECK | 11/24/2017 | | 11/27/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 11/27/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 11/22/2017 | | 11/24/2017 | | FAIL |
Jason C. Taylor
|
|
|
Need revised geotech report and ICC ESR-3982 report submitted. Jason Taylor ###-####.
|
Routing Walk-In (Zoning) | 11/22/2017 | 11/22/2017 | 11/22/2017 | P | PASS |
Jeff Lowe
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/22/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/22/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/22/2017 | | DONE |
|
|
|
|
Application received | | | 11/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 20 2017 9:58AM
|