DOC - Permit Finaled | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 8/3/2018 | 8/6/2018 | 8/6/2018 | A | PASS |
Dave Hannah
|
|
|
Jay-ADU ready for C of O-floodplain cert if signed off-no energy inspection Phone #: ###-####
|
Elevation Cert Rec'd-Final | | | 8/3/2018 | | DONE |
|
|
|
Final elevation certificate has been recieved signed off for JCT
|
BLD-Final | 7/25/2018 | 7/27/2018 | 8/1/2018 | P | PEND |
Dave Hannah
|
|
|
Please give me an hour notice so I can meet you there. Thanks. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole needs final flood plan cert
|
Zoning Approval | 7/24/2018 | 7/24/2018 | 7/24/2018 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Framing/Rough-in | 5/31/2018 | 6/1/2018 | 6/4/2018 | A | PASS |
Dave Hannah
|
|
|
Call half before // Caleb Phone #: ###-####
|
Elevation Cert Rec'd-Midconst | | | 6/4/2018 | | DONE |
|
|
|
|
BLD-Foundation | 4/19/2018 | 4/19/2018 | 4/19/2018 | A | PASS |
Dave Hannah
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 4/17/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Dave Hannah
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro ftg ok
|
BLD-Footing | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PASS |
Dave Hannah
|
|
|
JAY Phone #: ###-#### ftg stem wall and slab
|
Issue PAID IN FULL permit | | | 2/9/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 2/8/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 12/14/2017 | 12/15/2017 | 2/8/2018 | | PASS |
Josh Bogle
|
|
|
ADU plans incomplete - filed w/ Josh, waiting for the rest
|
Routing - PLAN CHECK | 2/8/2018 | | 2/8/2018 | | PASS |
Josh Bogle
|
|
|
|
Telephone call | | | 2/8/2018 | | DONE |
Christina Prado
|
|
|
left message with GC, gave fees due and advised RP is required prior to issuance
|
Routing - MECHANICAL | 2/8/2018 | | 2/8/2018 | | PASS |
Troy James
|
|
|
Manual j report not required. Ductless heat pump. Energy star fan for mechanical ventilation.
|
Inspection Record Card- Bld | | | 2/8/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/8/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2018 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 2/8/2018 | | DONE |
Christina Prado
|
|
|
Need:
RP (Homeowner or GC provided?)
|
Routing - Design Review | 12/15/2017 | | 2/7/2018 | | PASS |
Ted Vanegas
|
|
|
|
Routing - Addressing | 12/15/2017 | | 2/6/2018 | | PASS |
Doug Chausow
|
|
|
ADU Address: 914 E Krall St
|
Routing - PUBLIC WORKS | 2/6/2018 | | 2/6/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Flood Plain | 2/6/2018 | | 2/6/2018 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
|
Plan Reviewer's activity | | | 2/6/2018 | | DONE |
Josh Bogle
|
|
|
double-checked applicants info and started the routing - JAB
|
Routing Walk-In (BLD) | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | FAIL |
Josh Bogle
|
|
|
plans still lack needed details
|
Routing Walk-In (BLD) | 12/28/2017 | 12/28/2017 | 12/28/2017 | A | FAIL |
Josh Bogle
|
|
|
talked through info still needed using the 406 checklist
|
Route to Impact Fee Review | 12/15/2017 | 12/18/2017 | 12/20/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan Reviewer's activity | | | 12/20/2017 | | FAIL |
Josh Bogle
|
|
|
left Msg w/ Jay re: missing details; energy code, venting, elevations, floor plan
|
Routing PW Sewer Rating | 12/18/2017 | | 12/18/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing Walk-In (Zoning) | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | DONE |
Candy A. Nichols
|
|
|
|
Routing Walk-In (Zoning) | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
KayCee Babb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/14/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/14/2017 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 12/6/2017 | 12/6/2017 | 12/6/2017 | A | FAIL |
Josh Bogle
|
|
|
resubmitalls were dropped off but we have no application nor the rest of the submittal docs - holding as a level 2 on task list
|
Plan resubmittals received | | | 12/6/2017 | | DONE |
|
|
|
2 copies of A1,A2,A3 and structural calculations stamped and taken to JAB
|
Routing Walk-In (BLD) | 11/30/2017 | 11/30/2017 | 11/30/2017 | P | PASS |
Josh Bogle
|
|
|
questions about what the homeowner brought in. just a consult, no review
|
Routing Walk-In (Zoning) | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | PASS |
KayCee Babb
|
|
|
|
Routing Walk-In (BLD) | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 11/20/2017 | | FAIL |
Brian McGowan
|
|
|
Need larger plans that are legible. (brought in 8 1/2 x 11 and plans are at 1/4"=1'-0")
|
Routing - PLAN CHECK | 11/20/2017 | | 11/20/2017 | | FAIL |
Brian McGowan
|
|
|
|
Application received | | 11/20/2017 | | | |
|
|
|
|