BLD-Final | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PASS |
Dave Hannah
|
|
|
Vince Phone #: ###-####
|
DOC - Permit Finaled | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 7/13/2018 | 7/16/2018 | 7/16/2018 | A | PEND |
Mike Jordan
|
|
|
Vince Phone #: ###-####. Provide blower door test results and post. everything else ok.
|
BLD-Energy code compliance | 4/26/2018 | 4/26/2018 | 4/26/2018 | P | PASS |
Jim Sly
|
|
|
Vince Phone #: ###-####
|
BLD-Framing/Rough-in | 4/20/2018 | 4/20/2018 | 4/20/2018 | P | PASS |
Jim Sly
|
|
|
Vince Phone #: ###-####
|
BLD-Wall Bracing | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PART |
Mike Jordan
|
|
|
Vince Phone #: ###-####. INstall missing blocking on garage wall, provide the portal frame over windows, south wall. ok to tyvek and install windows.
|
BLD-Foundation | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Jim Sly
|
|
|
Derick Phone #: ###-####
|
BLD-Footing | 3/5/2018 | 3/5/2018 | 3/5/2018 | P | PASS |
Jim Sly
|
|
|
Derick Phone #: ###-####-2650
|
Issue PAID IN FULL permit | | | 3/2/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/19/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 12/18/2017 | 12/18/2017 | 1/19/2018 | | PASS |
Josh Bogle
|
|
|
1st done - thermal envelop unclear
|
Routing - PLAN CHECK | 1/19/2018 | | 1/19/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 1/19/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 1/12/2018 | | 1/18/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 1/12/2018 | | 1/16/2018 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
Routing - PLANNING | 1/12/2018 | | 1/12/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Plan Reviewer's activity | | | 1/11/2018 | | DONE |
Josh Bogle
|
|
|
sent Eplan resubmit back, per applicant's request - JAB
|
Plan Reviewer's activity | | | 1/9/2018 | | FAIL |
Josh Bogle
|
|
|
I did not accept an E-plan resubmittal because the versioning was incorrect.
|
Plan assigned to (BJM) | 12/13/2017 | 12/13/2017 | 12/18/2017 | | DEFR |
Brian McGowan
|
|
|
12/26 sfd L1 ePlan
|
Routing - PLAN CHECK | 12/13/2017 | | 12/18/2017 | | FAIL |
Josh Bogle
|
|
|
no Plan Check - project will need substantial redesign per Planning
|
1st review completed | | | 12/18/2017 | | FAIL |
Josh Bogle
|
|
|
no Plan Check - project will need substantial redesign per Planning
|
Route to Impact Fee Review | 12/13/2017 | 12/16/2017 | 12/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 12/13/2017 | | 12/14/2017 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/13/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/13/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/13/2017 | | PASS |
|
|
|
|
Routing - Addressing | 12/13/2017 | | 12/13/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/13/2017 | | 12/13/2017 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 11/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 20 2017 1:39PM
|
Routing - PLANNING | 12/13/2017 | | | | FAIL |
|
|
|
Garage needs to be 20' from edge of common drive
|