BLD-Final | 12/19/2017 | 12/20/2017 | 12/20/2017 | P | PASS |
Brandon Shaw
|
|
|
Final can be done early in the PM or if you are out there earlier, you can go later in the AM. Jimmy will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
DOC - Permit Finaled | 12/20/2017 | 12/20/2017 | 12/20/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Footing | 12/14/2017 | 12/15/2017 | 12/15/2017 | P | PASS |
Brandon Shaw
|
|
|
Footing inspection can be done in the PM tomorrow. Jimmy will be doing the installation and his cell number ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
Routing Walk-In (Zoning) | 12/12/2017 | 12/12/2017 | 12/12/2017 | A | PASS |
Sue Cummings
|
|
|
corrected plans O.K.
|
Plan assigned to (JAB) Josh | 11/21/2017 | 11/21/2017 | 12/12/2017 | | PASS |
Josh Bogle
|
|
|
1st done - Planning issues
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/12/2017 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 12/12/2017 | | DONE |
|
|
|
met
|
Inspection Record Card- Bld | | | 12/12/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/12/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/1/2017 | | 12/4/2017 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 11/21/2017 | | 11/22/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 11/22/2017 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | | 11/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2017 10:56AM
|
Plans ACCEPTED BY PLAN TECH | | | 11/21/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/21/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/21/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 12/1/2017 | | | | FAIL |
Sue Cummings
|
|
|
No changes were made to the site plan. New construction needs to meet setbacks.
|
Routing - PLANNING | 11/21/2017 | | | | FAIL |
|
|
|
The home is located on a separate lot, requires 5 ft. setback on side. The site plan does not represent correct shape of lot/current structures
|