BLD-Final | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | PASS |
Jim Sly
|
|
|
Barry-call for access Phone #: ###-####
|
DOC - Permit Finaled | 10/19/2018 | 10/19/2018 | 10/19/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
BLD-Wall cover | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
BLD-Framing/Rough-in | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | NR |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/24/2018 | 5/25/2018 | 5/29/2018 | P | PART |
Dave Hannah
|
|
|
Barry Phone #: ###-#### c/n on site ok to insulate
|
BLD-Wall Bracing | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Mike Jordan
|
|
|
Shear // Berry Phone #: ###-####
|
BLD-Wall Bracing | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | FAIL |
Mike Jordan
|
|
|
Berry Phone #: ###-####. Install missed blocking on shop on either side of west roll up door. Nail rv garage front at 2 inches on center and install missed blocking and nail in RV bay.
|
BLD-Wall Bracing | 5/3/2018 | 5/4/2018 | 5/4/2018 | P | NR |
Mike Jordan
|
|
|
late afternoon // Barry Phone #: ###-####. Will reschedule.
|
BLD-Foundation | 2/4/2018 | 2/5/2018 | 2/5/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 2/1/2018 | 2/2/2018 | 2/2/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
Issue PAID IN FULL permit | | | 1/12/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/11/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/11/2018 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2018 | | DONE |
|
|
|
called Barry to let know permit is ready and how much is owed
|
Permit Ready to Issue | | | 1/11/2018 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 12/7/2017 | 12/7/2017 | 1/10/2018 | | PASS |
Josh Bogle
|
|
|
1st done - Planning issues, also shop questions
|
Routing - PLANNING | 1/10/2018 | | 1/10/2018 | | PASS |
Leon Letson
|
|
|
|
Routing - PLAN CHECK | 1/10/2018 | | 1/10/2018 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/10/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2018 | | DONE |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 12/22/2017 | | DONE |
Josh Bogle
|
|
|
quick look at resubmittal, e-mail to applicant to say "looks good"
|
Plan resubmittals received | | | 12/21/2017 | | DONE |
|
|
|
resubmittals received 2 sets of each sheet 1, 3, 5, 7
& 8-took to JAB
|
1st review completed | | | 12/7/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 11/30/2017 | | 12/7/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 11/27/2017 | | 11/30/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PUBLIC WORKS | | | 11/27/2017 | | PASS |
|
|
|
|
Route to Impact Fee Review | 11/22/2017 | 11/25/2017 | 11/24/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 11/22/2017 | | 11/24/2017 | | PASS |
Laura Hunter
|
|
|
|
Plan assigned to (BJM) | 11/22/2017 | 11/22/2017 | 11/22/2017 | | DEFR |
Brian McGowan
|
|
|
12/5 sfd L1 paper
|
Plans ACCEPTED BY PLAN TECH | | | 11/22/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 11/22/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/22/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | 11/22/2017 | | | |
|
|
|
|
Routing - PLANNING | 11/27/2017 | | | | FAIL |
|
|
|
Does not meet 30 ft. rear setback. 2,006 sf. shop reuires zoning certificate.
|