Permit Information
Permit NumberBLD17-04351
StatusFinaled
Name DEBELLOY CONSTRUCTION
Site Address 1808 W JEFFERSON ST
Project NameBicandi Detached Garage
Customer Number 
ePlanReviewYes
Description
Permit to build 441sq' detached garage with 331sq' office space above. There are 1hr fire details for the reduced setback side. All work per plans & and local code. Separate electrical, plumbing, & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/5/20195/6/20195/6/2019PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by kevin debelloy
DOC - Permit Finaled5/6/20195/6/20195/6/2019PPASS
DetailsBrandon Shaw
BLD-Final4/23/20194/24/20194/25/2019PNR
DetailsTony Young
Inspection requested via web by kevin debelloy
BLD-Framing/Rough-in9/13/20189/14/20189/14/2018APASS
DetailsDave Hannah
Inspection is for exterior type x fire barriers Phone #: ###-#### Inspection requested via web by kevin debelloy
BLD-Energy code compliance9/6/20189/6/20189/6/2018APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by kevin debelloy
BLD-Framing/Rough-in9/4/20189/4/20189/4/2018PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by kevin debelloy
BLD-Framing/Rough-in8/24/20188/24/20188/24/2018PFAIL
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by kevin debelloy c/n on site
BLD-Framing/Rough-in8/23/20188/23/20188/23/2018PNR
DetailsJim Storey
Inspection requested via web by kevin debelloy
BLD-Foundation6/12/20186/12/20186/12/2018PPASS
DetailsJim Storey
Pour is set for 3:30 Phone #: ###-#### Inspection requested via web by kevin debelloy
BLD-Footing6/11/20186/11/20186/11/2018PPASS
DetailsBrandon Shaw
Pour is scheduled for 3:00 Phone #: ###-#### Inspection requested via web by kevin debelloy
BLD-Footing6/11/20186/11/20186/11/2018PCANC
DetailsTony Young
Concrete is scheduled for 1:00 Phone #: ###-#### >> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
Issue PAID IN FULL permit  12/15/2017 DONE
OVERRIDE  12/13/2017  
Plan assigned to (JAB) Josh11/30/201711/30/201712/13/2017 PASS
DetailsJosh Bogle
1st done - issues with structure, braced walls, fire assemblies, etc.
Routing - PLAN CHECK12/13/2017 12/13/2017 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK12/13/2017 12/13/2017 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  12/13/2017 DONE
DetailsJosh Bogle
ESC yes - Energy yes
Permit Ready to Issue  12/13/2017 DONE
NEED
RP-MET
GC FORM
Routing - PLAN CHECK11/30/2017 12/4/2017 FAIL
DetailsJosh Bogle
1st review completed  12/4/2017 FAIL
DetailsJosh Bogle
Routing - PLANNING11/30/2017 12/1/2017 PASS
DetailsColleen T Carroll
Not to be used as an Accessory Dwelling Unit!
Plans ACCEPTED BY PLAN TECH  11/30/2017 DONE
Recd Pcfee & Taken To Pln CK  11/30/2017 DONE
No fee taken at intake, 406
Intake Approval  11/30/2017 PASS
Application received  11/29/2017 DONE
Application submitted via PDS Online on Nov 29 2017 2:09PM