Print Statement | | | 12/13/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/13/2019 | | DONE |
|
|
|
Emailed invoice to Jessica@rrccontractors.com after speaking with her regarding another permit BLD19-02156. Attached invoice.
|
Third Notice | | 4/16/2019 | 4/12/2019 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Third Notice | | 3/12/2019 | 4/11/2019 | | DONE |
|
|
|
mailed 4-12-19 with second follow up letter
|
Second Follow up | | | 4/11/2019 | | DONE |
|
|
|
|
Third Notice | | 2/11/2019 | 3/7/2019 | | DONE |
|
|
|
mailed 3-11 with first follow up letter
|
First Follow up | | | 3/7/2019 | | DONE |
|
|
|
|
Third Notice | | 1/13/2019 | 2/6/2019 | | DONE |
|
|
|
mailed 2-11-19
|
Third Notice | | 12/18/2018 | 1/8/2019 | | DONE |
|
|
|
mailed 1-11-19
|
Second Notice | | 11/23/2018 | 12/13/2018 | | DONE |
|
|
|
mailed 12-14
|
First Notice | | 10/20/2018 | 11/13/2018 | | DONE |
|
|
|
mailed 11-14
|
Print Occupancy Form | | | 10/10/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/10/2018 | | DONE |
|
|
|
|
BLD-Final | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####***FIR permit not finaled***
|
Temporary Occupancy | 10/2/2018 | 12/31/2018 | 10/2/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Print Occupancy Form | | | 10/2/2018 | | DONE |
|
|
|
|
BLD-Final | 9/27/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Dave Hannah
|
|
|
zack Phone #: ###-####
|
FIRE-Final Inspection | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Jim Page
|
|
|
Previously noted items have been completed, final life fire safety inspection for area of work complete.
zack Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 9/27/2018 | | DONE |
|
|
|
Plan mod
|
Inspection Record Card- Bld | | | 9/27/2018 | | DONE |
|
|
|
|
Routing - FIRE | 9/25/2018 | 9/25/2018 | 9/26/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
alternates shall be met
|
Plan assigned to (JG) | 9/20/2018 | 9/20/2018 | 9/26/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod for GSA
|
Permit Ready to Issue | | | 9/26/2018 | | DONE |
|
|
|
PLAN MOD
|
Routing - PLAN CHECK | 9/25/2018 | | 9/26/2018 | | PASS |
Javier Guzman
|
|
|
|
Plan Reviewer's activity | | | 9/24/2018 | | DONE |
Javier Guzman
|
|
|
Plan Mod prescrren failed
Provide the following and upload:
• Provide revised plan sheet G1.6 with Architects stamp that is signed and dated
• Provide a floor plan showing location of the referenced combination locks from the uploaded letter “Boise_RA_CDX-10_Exemption_Letter_2018_09_20_15_18_29_545”
• Provide an updated door hardware schedule
|
Plan Reviewer's activity | | | 9/24/2018 | | DONE |
Javier Guzman
|
|
|
Previous request below not addressed 9/24/2018
Failed plan mod prescreen
Provide the following and upload:
• Provide a floor plan showing location of the referenced combination locks from the uploaded letter “Boise_RA_CDX-10_Exemption_Letter_2018_09_20_15_18_29_545”
|
BLD-Final | 9/19/2018 | 9/20/2018 | 9/21/2018 | P | NR |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
FIRE-Final Inspection | 9/20/2018 | 9/21/2018 | 9/20/2018 | A | CANC |
Jim Page
|
|
|
changes have not been addressed
Zack Phone #: ###-####
|
FIRE-Final Inspection | 9/19/2018 | 9/20/2018 | 9/20/2018 | A | CANC |
Adele J Schaffeld-Griffin
|
|
|
Zach Phone #: ###-####
|
FIRE-Final Inspection | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1-door hardware needs to be installed to meet alternate.
2-exit sign needs added in hallway now that door installed and blocks view
3-possible revised exit plan, see architect.
4- need electrical final
Zack Phone #: ###-####
|
BLD-Conference | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
FIRE-Conference | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | DONE |
Adele J Schaffeld-Griffin
|
|
|
Confrence with Ron Johnson- This was a conference to cover requirements for TCO of main tenant space with phase two being the completion of the two storage rooms. Fire alarm permit has been pulled. FIR18-00476. All fire life safety items would need to be completed for TCO, including testing the operation of the door hardware to confirm operation per the accepted alternate. Zack Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/31/2018 | 8/31/2018 | 8/31/2018 | P | PASS |
Mike Jordan
|
|
|
Zack Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/29/2018 | 8/29/2018 | 8/30/2018 | P | PEND |
Dave Hannah
|
|
|
Zach Phone #: ###-#### ok afther elec rough ins
|
BLD-Framing/Rough-in | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/14/2018 | | DONE |
|
|
|
|
Telephone call | | | 5/11/2018 | | DONE |
|
|
|
spoke with jeff likes informing him that this permit is showing it will expire in 18 days and recommended a extension request be sent in. stated it looks like review took a bit longer
|
Plan assigned to (JG) | 2/5/2018 | 2/5/2018 | 5/9/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/05 L3 GSA Office in Wells Fargo ePlan
|
Routing - PLAN CHECK | 5/2/2018 | | 5/9/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2018 | | DONE |
|
|
|
MET
Need
GC Form
Revised Cert of Value
|
Plan Reviewer's activity | | | 5/8/2018 | | DONE |
Jason Blais
|
|
|
Approved modifications to certain door hardware included in the plans and documents on site or in ePlanReview.
|
Routing - PLAN CHECK | 4/9/2018 | | 4/27/2018 | | FAIL |
Javier Guzman
|
|
|
after meeting with all parties invovled we came to the conclusion and recomendations for the door/door hardware ePlan sent back to architect
|
Plan Reviewer's activity | | | 3/15/2018 | | DONE |
Javier Guzman
|
|
|
At a quick glance ePlan resubmittal was sent back to architect to address the alternate code letter missing items and door hardware schedule not addressed. (no thorough review done)
|
Routing - FIRE | 3/7/2018 | 3/7/2018 | 3/9/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Routing - PLAN CHECK | 3/7/2018 | | 3/9/2018 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 2/6/2018 | 2/9/2018 | 2/7/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/6/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 12/21/2017 | | 2/6/2018 | | FAIL |
Javier Guzman
|
|
|
|
Plan assigned to (CJW) | 12/21/2017 | 12/21/2017 | 2/5/2018 | | DEFR |
Carl Westfall
|
|
|
(Jan 10 -15 days) (48 sheets) GSA Office in Wells Fargo
|
Routing - FIRE | 12/21/2017 | 12/21/2017 | 12/29/2017 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - MECHANICAL | 12/21/2017 | | 12/26/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 12/21/2017 | | 12/22/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 12/21/2017 | | 12/22/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/21/2017 | | 12/22/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan Reviewer's activity | | | 12/21/2017 | | PASS |
|
|
|
Plan intake review approved. Items deferred to plan review.
|
Intake Approval | | | 12/21/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl W accepted pre screen
|
Intake Approval | | | 12/2/2017 | | FAIL |
|
|
|
(12-2-17) Please see the circled items in the plan intake checklist. Please resolve each item as directed. CJW
|
Application received | | | 11/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 29 2017 3:32PM
|