BLD-Aging Inspection | 3/13/2019 | 3/13/2019 | 3/13/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 3/12/2019 | 3/12/2019 | 3/13/2019 | | FAIL |
Tony Young
|
|
|
|
Case Summary (BLD) | | | 11/29/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | FAIL |
Jim Page
|
|
|
City approved drawings and small documentation not on site, city approved drawings and associated small documents are required for the inspection process. Performed courtesy inspection for basic life safety items, no emergency lighting in shower/restroom area. Fire alarm modifications are required for area of work as noted in the fire conference notes entered in on 9JULY2018 under this BLD permit.
Fire alarm panel was showing a trouble at time of inspection, fire alarm panel needs to show a normal panel before life fire safety inspection.
John or ###-#### Breanna Phone #: ###-####
|
BLD-Final | 10/22/2018 | 10/23/2018 | 10/23/2018 | A | NR |
Tony Young
|
|
|
Terry Weymouth Phone #: ###-####,, needs f/l/s 1st,, no inspection made
|
BLD-Framing/Rough-in | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Tony Young
|
|
|
Terry Phone #: ###-####-please call 1 hr prior to meet,, ok pending trades
|
FIRE-Conference | 7/9/2018 | 7/9/2018 | 7/9/2018 | A | DONE |
Jim Page
|
|
|
Performed a rough in inspection for overhead fire sprinkler piping in remodeled area on the basement level, fire alarm modifications will be required (Fire alarm devices are hanging by the conduit that is attached to devices and as of 09JULY2018 there is no new permit in the PDS system for fire alarm modifications associated with this project). Fire alarm modifications will be required to be completed before life fire safety inspection. Also the property address has an outstanding permit for past fire alarm work, permit number is FIR14-00490. FIR14-00490 permit will be required to be finaled, no finals for the new fire alarm work or life fire safety will be signed off until FIR14-00490 is inspected and finaled.
|
BLD-Framing/Rough-in | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PART |
Tony Young
|
|
|
Art Phone #: ###-####,, needs trades,, sprinklers,, fireblocking,, etc.. walk through only
|
Issue PAID IN FULL permit | | | 3/30/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/30/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/2/2018 | 3/5/2018 | 3/2/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (RMH) | 2/20/2018 | 2/20/2018 | 3/2/2018 | | PASS |
Ron Hill
|
|
|
City Light Showers
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/2/2018 | | DONE |
|
|
|
Need
GC Form
Revised Cert of Value
|
Routing - PLAN CHECK | 1/25/2018 | | 3/2/2018 | | PASS |
Ron Hill
|
|
|
Pending Plumbing Resubmittal
|
1st review completed | | | 2/21/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 1/25/2018 | 1/25/2018 | 2/20/2018 | | DEFR |
Carl Westfall
|
|
|
(Feb 14 - 15 days) (12 sheets) City Lite Showers
|
Routing - PLUMBING | 2/12/2018 | | 2/12/2018 | | PASS |
Bill VanDegrift
|
|
|
architet to address water to toilets. if 1", tank type toilets will need to be installed and resubmit fixture schedule, if larger piping is found resubmit showing sizing.
|
Routing - FIRE | 1/25/2018 | 1/25/2018 | 1/30/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PUBLIC WORKS | 1/25/2018 | | 1/26/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 1/25/2018 | | 1/25/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/25/2018 | | 1/25/2018 | | FAIL |
Daryl Spivey
|
|
|
Idaho licensed engineered set of plumbing plans required for plumbing plan review
|
Routing - Addressing | 1/25/2018 | | 1/25/2018 | | PASS |
Laura Hunter
|
|
|
|
Plan Reviewer's activity | | | 1/25/2018 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 1/25/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl W accepted pre screen
|
Intake Approval | | | 1/11/2018 | | FAIL |
|
|
|
(1-11-18) Please see the circled items in the plan intake checklist (the ones without the OK). Please resolve each item as noted. CJW
|
Intake Approval | | | 12/2/2017 | | FAIL |
|
|
|
(12-2-17) Please see the circled items in the plan intake checklist. Please resolve each item as noted. CJW
|
Application received | | | 11/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 30 2017 11:08AM
|