BLD-Final | 4/1/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Dave Hannah
|
|
|
Spiral staircase riser blocks will be installed by about 930. Window stop will also be in. Thanks Phone #: ###-#### Inspection requested via web by Ryan Allen
|
DOC - Permit Finaled | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Allen returns on handrail and close up risers on spl stair
|
BLD-Wall cover | 12/31/2017 | 1/2/2018 | 1/2/2018 | A | PASS |
Dave Hannah
|
|
|
Inspection of wall insulation. Hoping to start hanging sheetrock on walls Tuesday mid morning. Requesting an early inspection if it''s doable. Thanks Phone #: ###-#### Inspection requested via web by Ryan Allen
|
BLD-Framing/Rough-in | 12/27/2017 | 12/28/2017 | 12/28/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection of air infiltration work prior to Insulation Phone #: ###-#### Inspection requested via web by Ryan Allen
|
BLD-Conference | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | DONE |
Dave Hannah
|
|
|
Would like to have walk through to verify previously done work. Phone #: ###-#### Inspection requested via web by Ryan Allen
|
Routing Walk-In (BLD) | 12/11/2017 | 12/11/2017 | 12/11/2017 | A | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 12/11/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 12/11/2017 | | 12/11/2017 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 12/11/2017 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 12/11/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/11/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/11/2017 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 12/4/2017 | 12/4/2017 | 12/4/2017 | P | FAIL |
Josh Bogle
|
|
|
stair and insulation issues
|
Routing - PLAN CHECK | 12/4/2017 | | 12/4/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 12/4/2017 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 12/4/2017 | | | |
|
|
|
|